Breaking News :   RTI activist demands urgent construction of multi-tier parking at GMC & SMGS to resolve acute parking crisis | Bus Stand police recovers Army personnel’s valuable box | Kisan Mela successfully organized at Ghordi, Udhampur - over 500 farmers participated | Mahaparinivan divas observed at Guru Ravi Dass Sabha | Preparations for Khichdi Mela to be completed by December 20: CM Yogi Adityanath | Shemrock Elites School celebrates Annual Day | Parents should encourage children to explore their extra-curricular talent: Balbir | 61st BSF Raising Day celebration held at frontier HQ Jammu | Prof Kul Bhushan Malhotra honored | Jammu Police XI triumphs over Jammu Media XI in Friendly Cricket Match | Retail Loan Outreach Program successfully conducted by Central Bank of India, Regional Office-Chandigarh | DM reviews Law & Order situation in Doda District | Anchor aweigh: MRSAFPI cadets Parasdeep & Yuvraj commissioned as Indian Navy Officers | Cong decides to intensify Talent Hunt for media & publicity Department | DC Kathua reviews progress under District Capex Plan | Samba police intensify drive against illegal mining; 5 more dumpers seized | Yogi Government's sports policy shines: Uttar Pradesh's Guru-Shishya duo wins gold and silver in Colombo, makes India proud | DM Rajouri orders immediate Suspension of VPN Services to prevent misuse | Amit tours Census Pre-Test Sites in Kashmir, Jammu to ensure successful culmination | Govt committed to promote Ladakh Pashmina globally, says LG Kavinder | Police tightens vigilance; two held with heroin at Balini bridge | MLA Arvind Gupta inaugurates Bakshi Nagar Gate, Ring Road at GMC Jammu | Rana attends annual day at Modern Institute of Creative Learning, Dharana Mendhar | Sakeena Itoo lays foundation stones for multiple flood mitigation projects | J&K Judicial Academy organizes workshop on Family Court Matters | Ashok Koul chairs review meeting in Srinagar | Police conducts mock drill at Bijbehara Railway Station to strengthen emergency response preparedness | J&K Police in organizes farewell function for retiring officers | All Bar Associations of Jammu Province Unite against New Tenancy Act, extend full support to JKHCBAJ | Gaurav hails India's 8.2% GDP surge, credits Modi Govt's reforms despite global headwinds | CS for giving push to strengthen credit linkage for artisans under PM Vishwakarma scheme | New homes for flood victims will foster stability: LG Sinha | Probe uncovers Dr Muzammil’s secret hideouts near Al Falah University | Delhi Court sends 3 doctors, preacher to 10-day judicial custody | Police seek details of foreign-educated doctors working in private hospitals | BSF alert to maintain ‘Zero Infiltration’ in Jammu: IG | India’s tradition rooted in fraternity: RSS Chief | ‘Op Sindoor’ brilliant example of civil-military fusion: Rajnath Singh | Night temperatures improve marginally | Outsourcing the Human Mind | The happy Era of Indian daughters in sports: When daughters became the pride of the Country | The happy Era of Indian daughters in sports: When daughters became the pride of the Country | The happy Era of Indian daughters in sports: When daughters became the pride of the Country | Remembering Triloki Nath Ganjoo ‘Vishwas’ | Remembering Triloki Nath Ganjoo ‘Vishwas’ | Back Issues  
 
news details
14 years on, Kangoloo-Pachound road yet to get completed
9/20/2020 10:52:26 PM
ASHWANI SHARMA
EARLY TIMES REPORT

UDHAMPUR, Sept 19: Going at a snail’s pace, the construction of Kangoloo-Pachound road is yet to get completed even after passage of 14 long years.
The work in hand may take more time as the completion of the project is nowhere in sight as the construction of this ill-fated road is perhaps has the least priority for those at the helm of affairs.
Work on the Kangoloo-Pachound road in tehsil Latti of district Udhampur was started in the year 2006 and presently the road is as dilapidated as it was before start of the construction work which clearly reflects the sincerity of the work culture of the concerned authorities.
“PMGSY Ramnagar is the agency which is executing the construction work,” said Akshay Malkan, Panch of Pachound.
He said that even earth work on the stretch has not been done in the 6 km part of the road and whenever the work on the road starts it gets halted within days on pretext of snowfall.
“This lackadaisical attitude of the concerned authorities is depriving people of the area from road connectivity,” the Panch said.
He appealed to the higher authorities to address the issue as soon as possible as the people are facing a lot of problems in the absence of a smooth road link.
When contacted, the PMGSY Executive Engineer Ramnagar, Satish Bhagat said that of the 16 km road, earth work on first stretch of 10 km is complete and for the remaining 6 km stretch there was some issue of clearance with the forest department which has now been sorted out.
The Executive Engineer also said that he has joined the department just a month back and assured that the issue will be resolved soon.
“By December this year the road will be completed in all respects,” he maintained.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU