Breaking News :   New freight train service big step for Kashmir apple growers: LG Sinha | LG attends closing ceremony of ‘Jashn-e-Dal’ | Will take up restoration of Jmu-Sgr highway with Union Minister: CM Omar | Cloudburst triggers flash floods in Reasi, no casualties | Day 21: Vaishno Devi Yatra remains suspended | Fruit growers’ union delegation meets LG | Doda: Educational institutions reopen after 3 weeks | Fraudster impersonating LG’s duty officer held in Rs 50 lakh scam: CBK | PM Modi lays foundation stone of projects worth around Rs 40,000 crore in Bihar | PM Inaugurates 16th armed forces’ conference at Eastern Command HQ | ITR filing deadline ends | DC Budgam calls for stronger enforcement & rehabilitation measures | DYSSO Samba launches major Inter-Zonal Sports tournament | Modi’s Governance: Gujarat Model to Bharatiya Model | Safety of Indians in America | Celebrating National Hindi Diwas | Parcel Train | FICCI FLO JKL rolls out Phase-4 of flood relief efforts in Jammu | Kuch Din Toh Aaiyein Ladakh Mein: LG Kavinder appeals in Navi Mumbai | Give your best to steer our nation ahead in growth & development: DyCM | MLA Sham Lal Sharma Pays Tribute to Sir M. Visvesvaraya on Engineers Day | Power shut down in several areas | Parcel cargo train from Kashmir to Adarsh Nagar Delhi flagged off | Javid Dar reviews status of NH-44 restoration | Only Aadhaar-authenticated users can book online general tickets in first 15 mins from Oct 1: Railways | DC Srinagar convenes DLSCC meeting | MLA Poonch, Ajaz Ahmed Jan offer condolences | Pakistan's terror nexus exposed again at UNSC: Gaurav | Randhawa reviews preparations at Bawe Wali Mata Mandir | Itoo flags off Dental Awareness Rally on Oral health hygiene | MLA Arvind Gupta inaugurates long-pending drain work at Rajpura | Boy injured in landmine blast in Anantnag, dies | Indian Army's first exclusive freight train on USBRL marks breakthrough | Punjab police busts cross-border weapon smuggling module with links to Pak | WPI inflation turns positive after 2 months, at 0.52% in August | SC to pass order on Sept 26 in suo motu case over lack of functional CCTVs in police stations | On Engineer's Day GCET Jammu inaugurates two-week induction programme | Crackdown on illegal mining continue on 2nd day | Ramban police recovers 30 lost mobile phones | Ravinder visits rain affected areas of Sunderbani, seeks relief, restorations on war footing | AIIMS Bathinda reaffirms zero tolerance for unethical practices | Indian Army organised interaction with prominent locals, media at Samote | JKEDI launches 3rd batch of Management Development Programs | GDC Bishnah celebrates Hindi Diwas in collaboration with J&K Rashtriya Bhasha Prachar Samiti | YCET conducts Induction Program | CCI raise serious issue of infrastructure crises | GCOE Jammu celebrates Hindi Diwas | MCM celebrates Hindi Diwas with fervour | Dogra Degree College celebrates Hindi Diwas | IIM Jammu hosts valedictory xeremony of Management Development Program on Corporate Governance | 3 cab drivers booked for violating traffic advisory, overcharging | Doda Police urges public to combat fake news, misinformation | PM Modi at 75: A legacy of vision, valor, Nation-Building: Rohiin Chandan | IRCS J&K provides relief material to flood-affected | JKAACL Jammu organizes one day symposium | Principal Secretary, Culture inaugurates hindi Pakhwada at K.L. Saigal Hall | SP North Vivek Shekhar Sharma releases devotional bhajan “Lad Fadeya Mahamai Da” | IGNOU Jammu successfully concludes Swachhata Pakhwada, reaffirming commitment to cleanliness | Back Issues  
 
news details
Z-Morh Tunnel to be completed by June, 2021, Zoji-La Tunnel by June, 2026
7/20/2020 11:33:03 PM
Early Times Report

SRINAGAR, July 20: Work on the 6.5-km Z-Morh tunnel, part of a strategic project for ensuring round-the-year connectivity between Kashmir valley and Ladakh region, is being undertaken on a war footing and it will be completed by June 2021, an official spokesman said here on Monday.
The spokesman said the information about the status of works on the Z-Morh tunnel was given at a meeting chaired by Jammu and Kashmir Chief Secretary BVR Subrahmanyam.
The chief secretary took the meeting of National Highway Infrastructure Development Corporation Limited (NHIDCL) to review the progress of various road projects being undertaken by them in Jammu & Kashmir.
With regard to Kashmir province, the meeting was informed that works on mega projects including Z-Morh tunnel and Zoji-La tunnel, are being undertaken on a war footing, the spokesman said.
“During the meeting, it was given out that Z-Morh tunnel project comprises 6.5-km tunnel, a 6-km approach road, two major bridges and one minor bridge. The project worth Rs.2,379 crores is expected to be completed by 30th June, 2021 and will provide round-the-year connectivity to Sonamarg,” he said. Work under Zoji-La project are also being taken up simultaneously.
It was mentioned that this project comprehensively includes a 14.15-km tunnel, an 18-km approach road between Z-Morh and Zoji-La tunnel as a single integrated package, besides carriageway, two snow galleries, four major bridges and 18 avalanche-protection dams, he added.
The project will cost Rs 4,430 crores and is expected to be operational by June, 2026, which will enable round-the-year connectivity to Ladakh, the spokesman added.
The Chief Secretary also reviewed progress of Baramulla- Gulmarg, Vailoo-Khanabal, Vailoo-Donipawa, Donipawa-Ashajipora road projects.
While reviewing the progress on road projects being executed in Jammu province, it was informed that a penalty of Rs 25 lakh has been imposed on the erring contractor for abandoning project works under third package of Jammu-Akhnoor road, and the works will resume shortly.
Meanwhile, Deputy Commissioner Jammu, maintained that 15-KMs stretch is currently encumbrance free and the rest will be made available by 30th July, 2020, so as to enable speedy completion of the project.
Moreover, Chief Secretary urged Divisional Commissioner, Jammu to allow contractors to bring in migrant labourers and equipment after observing the duly established protocols and standard operating procedures with respect to COVID -19 mitigation efforts.
The Chief Secretary emphasised on effective monitoring of projects to ensure their timely completion.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU