Breaking News :   Under PM Modi’s leadership India rising as major economic power, reclaiming its past glory: LG Sinha | One month after Kishtwar tragedy, mother’s unending wait for her missing kins continues | Safety audit of more than 50% schools pending, resumption of offline classes uncertain | Land subsidence crumbles hopes, dreams | PM Modi visits Aizawl, Mizoram; lays foundation stones of works worth over Rs 9,000 crore | Empower elected J&K Govt in accordance with aspirations of people: CM Omar | Doda: Markets return to life as restrictions eased for 6 hours | Schools to reopen tomorrow: DC | NCB Sgr busts major narcotics smuggling network; 3 arrested | Woman injured in bear attack | Drone seized near LoC | Want to make Manipur symbol of peace, prosperity: PM Modi | UPITS 2025: A grand confluence of development, investment at India Expo Mart | Cultural Unit Srinagar of DIPR organizes cultural programme | Div Com stresses on collaborative efforts for Aerospace Safety | Justice Vinod Chatterji Koul inaugurates 3rd National Lok Adalat at Baramulla | Preparations for Sewa Parv-2025 reviewed at Kupwara | CM instructs for enhanced facilities for attendants, strengthening of sanitation in hospital | Jammu Rural Police Khour arrests third absconder in FIR 107/2023 case | Miran Sahib police arrests one accused in attempt to murder case | PHC Chatroo, HW Centre Udil Gojran receive Prestigious NQAS Certification | DC Udhampur reviews preparations for Sewa Parv-2025 | DLIC approves 334 Youth Entrepreneurship cases under Mission Yuya in Kulgam | ADC Bhaderwah convenes meeting with members of civil society | DC Kulgam visits District Hospital; directs expeditious completion of ongoing projects | National Lok Adalat held at ADR Centre Court Complex Kathua | Rich Harvest hosts CBSE capacity building programme | White water rafting expedition flagged off by Tiger Division | DAV Players’ outshine in Maharaja Ranjit Singh Cup | Inspiring Celebration of Hindi Diwas held | Apni Party Delegation Submits Memorandum to Joint Commissioner | Missing person traced, reunited with family | Quiz Competition on Population Geography held at GCW Udhampur | Cadet Swastik Sharma Brings National Glory to PWS Pathankot | Can a combined MBBS-Ayurveda degree produce competent doctors? | Before Physics, There Was Math: A Journey Through Human History” | Footpaths: The Lost Spaces of Urban India | C.P Radhakrishnan: - From RSS Worker to Constitutional Custodian | Back Issues  
 
news details
Hundreds of PMGSY road projects face time overrun
12/25/2020 12:13:42 AM

EARLY TIMES REPORT

JAMMU, Dec 24: Despite clear guidelines of specified time period for completion of road projects under Pradhan Mantri Gram Sarak Yojna (PMGSY), there are still hundreds of such projects, which have been facing undue delay in their completion.
Sources told Early Times that as per guidelines which envisage that completion of the road projects should be within a period of nine months from the date of issue of work order but not exceeding twelve months in any case. However, the time limit has been exceeded up to eighteen months for completion of work on roads in hilly areas.
They further said that over 250 road projects under PMGSY, only few dozen road projects were completed within the stipulated time wherein around 90 road projects including Jammu (6), Udhampur (19), Ramban (5), Rajouri (19), Ganderbal (7), Anantnag (12), Baramulla (5), Kupwara (14) and Leh (3) which were taken up for execution under Phases IV to IX were completed with delay ranging from 2 months to 8 years.
They further informed that over 40 road projects for connecting 30 habitations including Udhampur (14), Ramban (5), Rajouri (2), Ganderbal (2), etc. taken up for execution under Phases V to X at a sanctioned cost of Rs 190 cr, on which expenditure of Rs 80 cr was incurred could also not be completed within stipulated period due to land dispute, non-clearance from forest department, etc. “Even after a delay of more than seven years from the date of allotment, these roads were not completed. Areas targeted to be connected remained unconnected,” they alleged.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU