Breaking News :   Doctors - The Unsung Heroes of Healthcare | WHEN RS 10 FEELS EXPENSIVE ON A CART, BUT NOT IN A CAFE | Urdu For Naib Tehsildar Recruitment Test | Yatri Niwas in Srinagar | LG Sinha inaugurates SASB Yatri Niwas at Pantha Chowk | LG launches campaign for zero-waste pilgrimage | 'Amarnath Yatra arrangements upgraded' | Heroin worth Rs. 420 crore seized in Rajasthan; Pak-based smuggler, Canada handler named | Within minutes after formation of PAC, NC mocks Sajad Lone’s new political front as ‘BJP’s B-Team’ | CM Omar calls for revival of buyer-creator relationship at SKICC Meet | Salal Dam gates opened amid rising Chenab Water levels | DGP chairs joint security review meeting in Anantnag, visits key areas | Major reshuffle in ACB J&K | From warzone to homeland: Kashmiri students hail India’s rescue mission with tricolour cheers | Security Forces bolster security with hi-tech gadgets | Token distribution for registration begins | Security Forces conduct joint mock drill | India woman footballer Soumya undergoes surgery after nasal bone fracture | Lack of variety in India's bowling attack is concerning: Chappell | National-level minor boxer alleges sexual harassment by woman coach | | MCM launches workshop on Skill Development, Entrepreneurship | GDC Kathua honours NCC Cadet Mohit Kanathia with grand welcome ceremony | Missing person traced from Pallanwala within 2 days | JKHCBAJ unveiles Portrait of Maharaja Hari Singh ji, inaugurated | Four JKAS Officers transferred In Transport Dept Reshuffle | J&K police arrest 87 in drug crackdown, seize narcotics worth Rs 2.42 Cr | Gross GST collections double in 5 years to record Rs 22.08 trillion in FY25 | Srinagar police attaches residential property worth Rs 50 lakh | SKUAST-K holds workshop in Gurez to promote revival of heritage crops | Reasi police solves two theft cases in Katra, accused arrested, stolen property | Union Minister Piyush Goyal to lead transformative FTII Traders conclave | Congress holds impressive Jai Hind Yatra in Poonch City, salutes armed forces, martyrs | Warm, affectionate farewell accorded to retirees of Agriculture Department Jammu | DC Shopian inspects work of rural development projects at Keller | Former JKNPP leaders, senior workers join Apni Party | Committee on Petitions holds meeting in Srinagar | 6000 students participate in NMMSS examination | Ladakh PM Vishwakarma artisans participate in MSME Day celebration | Vi Business’s ready for next - India’s largest digital advisory celebrates growth on MSME day | Indian Army pays tribute to Ex-Serviceman | Civil Defence, Jammu started 5 days CD training programme | Warm send off accorded to Sardar Dharminder Singh Bhargav Head Pharmacist from DHS-J | JKEDI concludes second batch of MDPs in 10 districts | Handicrafts, Handloom Deptt condoles demise of father of Mussrat Islam | IGNOU launches certificate programme for Nurse Managers to Strengthen Managerial Competencies in Nursing Services | Back Issues  
 
news details
Hundreds of PMGSY road projects face time overrun
12/25/2020 12:13:42 AM

EARLY TIMES REPORT

JAMMU, Dec 24: Despite clear guidelines of specified time period for completion of road projects under Pradhan Mantri Gram Sarak Yojna (PMGSY), there are still hundreds of such projects, which have been facing undue delay in their completion.
Sources told Early Times that as per guidelines which envisage that completion of the road projects should be within a period of nine months from the date of issue of work order but not exceeding twelve months in any case. However, the time limit has been exceeded up to eighteen months for completion of work on roads in hilly areas.
They further said that over 250 road projects under PMGSY, only few dozen road projects were completed within the stipulated time wherein around 90 road projects including Jammu (6), Udhampur (19), Ramban (5), Rajouri (19), Ganderbal (7), Anantnag (12), Baramulla (5), Kupwara (14) and Leh (3) which were taken up for execution under Phases IV to IX were completed with delay ranging from 2 months to 8 years.
They further informed that over 40 road projects for connecting 30 habitations including Udhampur (14), Ramban (5), Rajouri (2), Ganderbal (2), etc. taken up for execution under Phases V to X at a sanctioned cost of Rs 190 cr, on which expenditure of Rs 80 cr was incurred could also not be completed within stipulated period due to land dispute, non-clearance from forest department, etc. “Even after a delay of more than seven years from the date of allotment, these roads were not completed. Areas targeted to be connected remained unconnected,” they alleged.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU