Breaking News :   Forces thwart Pak’s Hamas-style attack on Jammu | In Pak terrorists are given state funerals: Foreign Secretary | Terror nexus exposed: Al-Qaeda backs Pak | Jammu mosques, madrassas open for displaced border residents | Amid cross border shelling, CM Omar reviews situation in border districts | Breeding Ground for fidayeen, links to Hamas, stockpiled NATO arms | PM meets secretaries, stresses on alertness | Masood Azhar’s brother killed: BJP | LG Sinha chairs high-level meeting, reviews preparedness | Army uses Harpy drones to target enemy air defence systems | Pak attempts to attack 15 places in North, Western India foiled | 100 terrorists, aides killed in strikes: Rajnath at All-Party Meeting | SDRF conducts Mock Drill Exercise at IIT Jammu | Developed India strikes back at provocateurs by entering their hideouts: CM Yogi | Cash Row: CJI recommends impeachment of Justice Yashwant Varma, says sources | Amit terms AI as biggest disruptive tech of 21st Century in MZU National Workshop | Salman Sagar appointed as vice provincial president of JKNC | SET exam in J&K, Ladakh UTs postponed | ASCOMS & Hospital to provide free treatment to border shelling victims | Rs 300 crore BrahMos Missile Unit set to be inaugurated in Lucknow on May 11 | Any military attack on India will be met with very firm response: EAM Jaishankar | Vivek Bali Expresses Deep Grief Over Loss of Lives in Poonch Due to Pakistan Shelling | Reasi police foil illegal transportation of Khair logs in Katra area | 84 Bn CRPF Provides Relief to Flood-Affected Families | DC Jammu Reviews Zonal Master Plan for Ramnagar Eco-Sensitive Zone | Horticulture Department Kathua organises exposure visit | DC conducts on site inspection of restoration works on NH-44 | Power shut down in several areas | GMC Doda organises Blood Donation Camp | HPS participates in annual “Save Water, Save Birds” campaign | World Red Cross Day observed at Udhampur | Reasi Administration celebrates World Red Cross Day | ACR reviews implementation of E-Waste Management Action Plan | Poonch Administration steps up restoration of Essential Services, Supplies | Arushi Kotwal of Doda Honoured by Union Minister Dr Mansukh Mandaviya | Mini-Super Bazar M-PACS Maitra inaugurated in Ramban | DC Reasi felicitates JK Board Class 10th 12th Toppers | Back Issues  
 
news details
5-years on, Baragoa-Tattapani road awaits completion
7/20/2021 12:15:41 AM
Avinash Azad
Early Times Report

Jammu, July 19: Kalakote Sub Division of Public Works (R&B) Division Nowshera has registered very poor performance in completion of works executed under its jurisdiction, as many roads despite work orders issued two years back, are yet to be blacktopped.
Advocate Vinod Sudan, a youth leader of Kalakote informed Early Times that work on four Kilometre long Baragoa-Tattapani road was executed in November 2016, but till date blacktopping has not been done.
“Earth and metal works of the road was completed in 2019, and tenders for the blacktopping works was also allotted to contractor two and half year ago, but the work didn’t commence,” he said, adding that if the works is completed around 450 families of the area would get road connectivity.
“This road will also reduce at least 10 kilometres distance between Kalakote to Tattapani. Development of Tatapani town comes under Rajouri Development Authority (RDA), due to a popular hot water spring in the town, thousands of people visit the town in winter to take bath in the spring”, Sundan said, adding that it is believed that people get rid of joint pain and other ailments after taking bath in the spring.
“The existing road that connects Khargala-Tattapani is very narrow, and it is very difficult to pass if any vehicle comes from opposite directions, many people have lost their lives in road accidents on this stretch (Khargala-Tattapani). In 2016, the foundation stone of the road was laid by the local MLA and Minister Er. Abdul Gani Kohli”, he said, adding that nothing happened after that.
Executive Engineer, PWD Division Nowshera, Bikram Singh told Early Times that black topping works would start after the rainy season.
“I’m aware of the delay, I have directed the concerned contractor to complete the work as soon as possible, execution of black topping works during monsoon is a wastage of funds, so work will start after once the rainy season is over,” he added.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU