Breaking News :   Infighting Fear | 3-day Bocce Ball training camp-2025 concluded | Unrest, violence in Bangladesh sparks panic among families of J&K medical students | AI-generated fake tickets pose new challenge for railways | Terrorism, all other criminal activities under strict vigil of J&K Police: DGP Prabhat | Udhampur: Searches on to track down terrorists | Kashmir sees rise in night temperatures | Gold, Silver futures hit fresh peaks | PM Modi to chair 5th national conference of Chief Secys | School picnic permissions cancelled | Govt constitutes committee | Searches held near Bakshi Stadium | Major General Anupinder Bevli, VSM, ADG JK&L NCC directorate visits NCC training academy | Gdc darhal celebrates National Mathematics Day | National Mathematics Day celebrated at Govt HSS boys Poonch | University of Jammu inaugurates academic block for “Design Your Degree” program | Closing ceremony of 6th district Doda Taekwondo Championships 2025–26 concludes | Sweater distribution organised in GHS Deeli | Child welfare committee conducted safety awareness program | Amitava Chatterjee calls on LG Ladakh Kavinder Gupta | Devotees hold Solemn Tributes at Shri Martand Tirth | Tawi Welfare Society holds annual general body meeting | Yogi Govt presents Supplementary Budget of Rs 24,496.98 crore in Assembly | Career aspirations of high-performing students and the teaching profession | Success in career from digital efficiency | Back Issues  
 
news details
9 years on, Noorbagh-Qamarwari Bridge incomplete; Bemina hospital nowhere in sight
Saga of missed deadlines
8/22/2021 11:40:02 PM
Ishtiyaq Ahmad

Early Times Report

Srinagar, Aug 21: Even after nine years, Noorbagh-Qamarwari Bridge here is yet to be completed, similarly, despite elapsing of over seven years, the vital 500-bedded pediatric hospital in Bemina here is awaiting completion.
The work on Noorbagh-Qamarwari Bridge was started in 2013. The project was to be completed in four years. However, the project has been facing inordinate delay.
The project is being executed by Roads and Buildings department Kashmir. Noorbagh-Qamarwari Bridge popularly known as the “Cement Bridge” has historical importance in the Valley as it was the first bridge over the river Jhelum, which was constructed in concrete.
Notably, the bridge is an important link as it connects the Old City, Soura and other areas with North Kashmir.
Sources said that over the years the construction was stopped as there were several reasons behind the stoppage of the work and that it took long to remove the bottlenecks.
Shabir Ahmad, a local, said that the local population from both sides of river Jhelum extended their cooperation to authorities for completion of the work.
“Work on this bridge is going on at snail’s pace,” he said. The ongoing project has already missed several deadlines. Initially it was scheduled to be completed in 2014. Later, the deadline was extended upto March 2017 and then upto December 2018.
“It has become a routine for authorities to initiate a project, construct some pillars or plinth and then leave it half¬way,” a local said.
The locals urged Lieutenant Governor Manoj Sinha to direct concerned authorities to ensure completion of the bridge without further delay.
Chief Engineer, Roads and Building department, Er Showkat Jeelani Pandith said it is expected that the bridge will be completed by the end of this year (2021).
“There were several issues, which took long to be rectified,” he said, adding that the land issue was among the main bottlenecks that halted the work for a longer period.
“Many structures are to be removed and we are already on it,” he said.
Pertinently, the area where the bridge is being constructed is a congested place, thus simultaneously witnesses frequent traffic mess.
Bemina hospital misses 3 deadlines
After missing three consecutive deadlines in the past 7 years, the 500-bedded pediatric hospital at Bemina is still awaiting its completion.
The work on the hospital which was proposed to be a 200-bedded maternity care facility initially was started in 2013 during the National Conference (NC) regime. However, former Chief Minister, Late Mufti Mohammad Sayeed on October 17, 2015, gave it an extension and laid the foundation stone for 500-bedded Mother-Child Hospital.
However in 2019, the government accorded sanction to conversion of the 200-bedded Maternity Hospital and the 300 bedded Pediatric Hospital at Bemina, Srinagar into a full-fledged 500-bedded Children’s Hospital.
Sources in the Roads and Buildings (R&B) Department said that till now three deadlines for its completion —one in 2014, second in 2017 and third in 2018—had been missed and yet there is no clarity as to when it will be ready.
Officials within the Health Department said that as per the performance of the Roads and Building department, the project is likely to miss more deadlines.
Officials at GB Pant also said that if the hospital will be completed at an earliest it will ease the burden on the lone children hospital in the Valley.
“We have to manage patients from every nook and corner of Kashmir but if Bemina hospital is completed it will lessen the burden,” they said.
The Chief Engineer said that they have received State Administrative Council (SAC) approval to the construction of a 500-bedded pediatric hospital at Bemina, Srinagar and now the work will start.
He said that in the current year they are expecting the completion of the work.
Officials said that once complete, the hospital would be under the management control of the Government Medical College, Srinagar. “The hospital will strengthen the pediatric care facilities in Kashmir division, ease the burden of patient load on the existing tertiary level hospital, and ensure quality maternity, neonatal and pediatric care to the patients” they said.
Sources said that as per the previous plan, the GB Pant Hospital, located in the Sonawar area, will be converted into a general hospital as the staff and paediatric facilities from there would be shifted to the new premises.
It is to mention here that The Administrative Council (AC) headed by Lieutenant Governor, Manoj Sinha, recently gave fresh administrative approval to the construction of a 500-bedded pediatric hospital at Bemina, Srinagar.
“The project will be upgrading vital pediatric facilities on modern grounds and will be completed at an estimated cost of Rs. 114.81 crore. The new hospital will be equipped with all modern equipment for managing the high risk pediatric cases to further reduce the infant mortality rate,” the government has said.
It will also serve as the Centre of Excellence in pediatrics in Kashmir Division and will assist the Union territory in mitigating a possible third wave of COVID-19 pandemic.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU