Breaking News :   New freight train service big step for Kashmir apple growers: LG Sinha | LG attends closing ceremony of ‘Jashn-e-Dal’ | Will take up restoration of Jmu-Sgr highway with Union Minister: CM Omar | Cloudburst triggers flash floods in Reasi, no casualties | Day 21: Vaishno Devi Yatra remains suspended | Fruit growers’ union delegation meets LG | Doda: Educational institutions reopen after 3 weeks | Fraudster impersonating LG’s duty officer held in Rs 50 lakh scam: CBK | PM Modi lays foundation stone of projects worth around Rs 40,000 crore in Bihar | PM Inaugurates 16th armed forces’ conference at Eastern Command HQ | ITR filing deadline ends | DC Budgam calls for stronger enforcement & rehabilitation measures | DYSSO Samba launches major Inter-Zonal Sports tournament | Modi’s Governance: Gujarat Model to Bharatiya Model | Safety of Indians in America | Celebrating National Hindi Diwas | Parcel Train | FICCI FLO JKL rolls out Phase-4 of flood relief efforts in Jammu | Kuch Din Toh Aaiyein Ladakh Mein: LG Kavinder appeals in Navi Mumbai | Give your best to steer our nation ahead in growth & development: DyCM | MLA Sham Lal Sharma Pays Tribute to Sir M. Visvesvaraya on Engineers Day | Power shut down in several areas | Parcel cargo train from Kashmir to Adarsh Nagar Delhi flagged off | Javid Dar reviews status of NH-44 restoration | Only Aadhaar-authenticated users can book online general tickets in first 15 mins from Oct 1: Railways | DC Srinagar convenes DLSCC meeting | MLA Poonch, Ajaz Ahmed Jan offer condolences | Pakistan's terror nexus exposed again at UNSC: Gaurav | Randhawa reviews preparations at Bawe Wali Mata Mandir | Itoo flags off Dental Awareness Rally on Oral health hygiene | MLA Arvind Gupta inaugurates long-pending drain work at Rajpura | Boy injured in landmine blast in Anantnag, dies | Indian Army's first exclusive freight train on USBRL marks breakthrough | Punjab police busts cross-border weapon smuggling module with links to Pak | WPI inflation turns positive after 2 months, at 0.52% in August | SC to pass order on Sept 26 in suo motu case over lack of functional CCTVs in police stations | On Engineer's Day GCET Jammu inaugurates two-week induction programme | Crackdown on illegal mining continue on 2nd day | Ramban police recovers 30 lost mobile phones | Ravinder visits rain affected areas of Sunderbani, seeks relief, restorations on war footing | AIIMS Bathinda reaffirms zero tolerance for unethical practices | Indian Army organised interaction with prominent locals, media at Samote | JKEDI launches 3rd batch of Management Development Programs | GDC Bishnah celebrates Hindi Diwas in collaboration with J&K Rashtriya Bhasha Prachar Samiti | YCET conducts Induction Program | CCI raise serious issue of infrastructure crises | GCOE Jammu celebrates Hindi Diwas | MCM celebrates Hindi Diwas with fervour | Dogra Degree College celebrates Hindi Diwas | IIM Jammu hosts valedictory xeremony of Management Development Program on Corporate Governance | 3 cab drivers booked for violating traffic advisory, overcharging | Doda Police urges public to combat fake news, misinformation | PM Modi at 75: A legacy of vision, valor, Nation-Building: Rohiin Chandan | IRCS J&K provides relief material to flood-affected | JKAACL Jammu organizes one day symposium | Principal Secretary, Culture inaugurates hindi Pakhwada at K.L. Saigal Hall | SP North Vivek Shekhar Sharma releases devotional bhajan “Lad Fadeya Mahamai Da” | IGNOU Jammu successfully concludes Swachhata Pakhwada, reaffirming commitment to cleanliness | Back Issues  
 
news details
9 years on, Noorbagh-Qamarwari Bridge incomplete; Bemina hospital nowhere in sight
Saga of missed deadlines
8/22/2021 11:40:02 PM
Ishtiyaq Ahmad

Early Times Report

Srinagar, Aug 21: Even after nine years, Noorbagh-Qamarwari Bridge here is yet to be completed, similarly, despite elapsing of over seven years, the vital 500-bedded pediatric hospital in Bemina here is awaiting completion.
The work on Noorbagh-Qamarwari Bridge was started in 2013. The project was to be completed in four years. However, the project has been facing inordinate delay.
The project is being executed by Roads and Buildings department Kashmir. Noorbagh-Qamarwari Bridge popularly known as the “Cement Bridge” has historical importance in the Valley as it was the first bridge over the river Jhelum, which was constructed in concrete.
Notably, the bridge is an important link as it connects the Old City, Soura and other areas with North Kashmir.
Sources said that over the years the construction was stopped as there were several reasons behind the stoppage of the work and that it took long to remove the bottlenecks.
Shabir Ahmad, a local, said that the local population from both sides of river Jhelum extended their cooperation to authorities for completion of the work.
“Work on this bridge is going on at snail’s pace,” he said. The ongoing project has already missed several deadlines. Initially it was scheduled to be completed in 2014. Later, the deadline was extended upto March 2017 and then upto December 2018.
“It has become a routine for authorities to initiate a project, construct some pillars or plinth and then leave it half¬way,” a local said.
The locals urged Lieutenant Governor Manoj Sinha to direct concerned authorities to ensure completion of the bridge without further delay.
Chief Engineer, Roads and Building department, Er Showkat Jeelani Pandith said it is expected that the bridge will be completed by the end of this year (2021).
“There were several issues, which took long to be rectified,” he said, adding that the land issue was among the main bottlenecks that halted the work for a longer period.
“Many structures are to be removed and we are already on it,” he said.
Pertinently, the area where the bridge is being constructed is a congested place, thus simultaneously witnesses frequent traffic mess.
Bemina hospital misses 3 deadlines
After missing three consecutive deadlines in the past 7 years, the 500-bedded pediatric hospital at Bemina is still awaiting its completion.
The work on the hospital which was proposed to be a 200-bedded maternity care facility initially was started in 2013 during the National Conference (NC) regime. However, former Chief Minister, Late Mufti Mohammad Sayeed on October 17, 2015, gave it an extension and laid the foundation stone for 500-bedded Mother-Child Hospital.
However in 2019, the government accorded sanction to conversion of the 200-bedded Maternity Hospital and the 300 bedded Pediatric Hospital at Bemina, Srinagar into a full-fledged 500-bedded Children’s Hospital.
Sources in the Roads and Buildings (R&B) Department said that till now three deadlines for its completion —one in 2014, second in 2017 and third in 2018—had been missed and yet there is no clarity as to when it will be ready.
Officials within the Health Department said that as per the performance of the Roads and Building department, the project is likely to miss more deadlines.
Officials at GB Pant also said that if the hospital will be completed at an earliest it will ease the burden on the lone children hospital in the Valley.
“We have to manage patients from every nook and corner of Kashmir but if Bemina hospital is completed it will lessen the burden,” they said.
The Chief Engineer said that they have received State Administrative Council (SAC) approval to the construction of a 500-bedded pediatric hospital at Bemina, Srinagar and now the work will start.
He said that in the current year they are expecting the completion of the work.
Officials said that once complete, the hospital would be under the management control of the Government Medical College, Srinagar. “The hospital will strengthen the pediatric care facilities in Kashmir division, ease the burden of patient load on the existing tertiary level hospital, and ensure quality maternity, neonatal and pediatric care to the patients” they said.
Sources said that as per the previous plan, the GB Pant Hospital, located in the Sonawar area, will be converted into a general hospital as the staff and paediatric facilities from there would be shifted to the new premises.
It is to mention here that The Administrative Council (AC) headed by Lieutenant Governor, Manoj Sinha, recently gave fresh administrative approval to the construction of a 500-bedded pediatric hospital at Bemina, Srinagar.
“The project will be upgrading vital pediatric facilities on modern grounds and will be completed at an estimated cost of Rs. 114.81 crore. The new hospital will be equipped with all modern equipment for managing the high risk pediatric cases to further reduce the infant mortality rate,” the government has said.
It will also serve as the Centre of Excellence in pediatrics in Kashmir Division and will assist the Union territory in mitigating a possible third wave of COVID-19 pandemic.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU