CAG critical of delay in construction of Govt flats in J&K
10/14/2016 11:26:20 PM
Early Times Report

Jammu, Oct 14: The J&K Estate Department has drawn flak from the Comptroller and Auditor General (CAG) over delay in construction of flats for government employees in Jammu and Kashmir.
It noted that the department had not formulated any long term Perspective Plan for development of colonies in Srinagar and Jammu indicating actual requirement of accommodation and modalities for development of colonies.
The CAG in its report for the year ended March 31, 2015, said the work on construction of 400 residential flats taken up in June 2012 at an estimated cost of Rs 85.92 crore for completion within three working seasons, had not been completed as of March 2015 due to insufficient funding.
Audit scrutiny showed that the government had released Rs 5.30 crore (six per cent) during 2012-15 and against the targeted construction of 25 blocks (400 flats), work in three blocks had been completed to the extent of only 40 to 95 per cent whereas work on remaining 22 blocks (352 flats) was not started as of March 2015, CAG report said.
The Director Estates stated that 48 flats were expected to be completed by August 2015 and construction of pending flats could not be taken up due to non-release of funds by the Planning and Development Department.
The CAG report also said that the government quarters constructed on 18 kanals and nine marlas of land at Khazir Manzil and Dalgate Srinagar were gutted during 1989-90.
It said that no plan was formulated for re-development of these colonies during last 25 years.
The Director Estates stated that construction of Khazir Manzil had been delayed due to objections raised by the Lakes and Waterways Development Authority (LAWDA) and private hotels, it said.
"The reply furnished by the department was, however, not accompanied by any documentary evidence of objections raised by the LAWDA and private hotels", it said.
The CAG report said that land measuring 99.13 kanals identified in January 2012 at Sidhra in Jammu for construction of 400 flats had not been taken over from the Jammu Development Authority due to non-payment of cost of land despite lapse of three years.
The government constituted in October 2011 a Committee of group of officers for framing a comprehensive accommodation policy for secretariat employees but it has not formulated any such policy as of March 2015, it said.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU