Breaking News :   What Are the Implications of Renaming ? | Sanchar Saathi App: The Need for Balance Between Privacy and Security | Empower Divyangjans | Indian Navy synonymous with exceptional courage and determination: PM Modi | ‘Visit India to see Cheetah in all its splendour’ | Focus on enhancing diagnostic accuracy: LG Sinha | DGP visits Basantgarh, reviews ongoing operations | Pak-linked drug racket busted | ACB arrests Patwari, Chowkidar for taking Rs 10,000 bribe | Files chargesheet against AE | NIA Court rejects bail plea of narco-terror accused | ‘Trump didn’t play any role in India-Pak ceasefire’ | Gold falls by Rs 600 | Kashmir shivers, Pulwama records minus 5.6 C | SS Sodhi, president JKRA, elected to Board of Governing Members of National Rifle Association of India | Sant Kabir's message in verse relevant to forge unity: Devyani Rana | LG Kavinder Gupta calls for Equal Opportunities & Barrier-Free Access for Divyangjans | ADG Armed visits JKAP 8th Battalion, Reviews Operational and administrative functioning | Six Day Bharat Darshan Tour of Ramban district Flagged Off by DIG DKR Range | AIIMS Jammu proposes Global Centre for Artificial Intelligence in Healthcare | Court sentences two brothers in 2009 attack case | Three-day national conference NCAAPS-2025 commences at JU | EPFO Srinagar organizes seminar on PMVBRY at Pulwama | Inauguration of futuristic gym and railway club in Jammu Division as part of new initiative | Balbir paid obeisance at Rattan Vansh Devsthan, sought blessings | Traffic Violators will not spare at any cost: ARTO Neeraj Sharma | Back Issues  
 
news details
Delay in land transfer to PDD halts work on grid stations
7/5/2018 11:21:07 PM
Ishtiyaq Ahmad
Early Times Report
Srinagar, July 5: With overloading often causing disruption of electricity in Kashmir, work on construction of several grid stations has not been started due to non-transfer of land to Power Development Department.
The announcement for construction of grid stations was made years ago. But there has been no progress for their construction over the years.
An official of the PDD said that for construction of 220/33KV Grid Station at Batapora Tealbal Chatarhama, the land was yet to transfer to the PDD.
"The officials recently told Divisional Commissioner Kashmir in a meeting that land owners did not accept the rates offered by the government," the official said.
Similarly, no decision has been taken yet for transferring the land to the PDD for construction of 132/33KV grid station at Tangpora Batamaloo.
While for construction of grid station at Khanyar, the official said that file regarding transfer of industrial land to the PDD was lying with the administrative department.
An official document reveals that Divisional Commissioner Kashmir expressed "dismay" that transfer of land for the prestigious projects was not made over the years. He has directed the official to complete the process for transferring of land "on war footing" basis. "In case the land owners disagree to the official rates, compulsory mode of acquisition be adopted without any further delay," the documents revealed as Divisional Commissioner Kashmir having directed to officials.
While, the work on Alastang grid station is yet to be completed despite passing over eight years. The work on Alastang grid station was started in 2010 for transmission of electricity to Ganderbal district. However, very least work has been done on the project over the years and missed multiple deadlines.
The PDD official said that that there is an immense load on Pampore and Zainakote power grids from where electricity is being supplied to Srinagar, Ganderbal, and Pulwama districts.
"The two power grids face overloading resulting in frequent power cuts in Srinagar and Ganderbal districts. Presently, the Ganderbal gets electricity from Zainakote grid station and remains overloaded," the official said.
"Had these projects been completed, they would have reduced load on two existing power grids and helped the state to upgrade the power supply in the Valley," the official said.
The official said that department had sought tenders multiple times for completion of Alastang-Mirbazaar transmission line.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU