Breaking News :   Consumer Protection: The Backbone of a Resilient and Ethical Economy | The journey of accidents on unsafe roads the issue of security on roads in the country | Prez Murmu’s Message | CM Yogi Adityanath announces major relief for small, marginal farmers | When a farmer harnesses energy, the earth yields gold”: Chief Minister | Modern LHB rake on Balurghat–Kolkata–Balurghat express inaugurated | Kashi Tamil Sangamam 4.0: VC urges learning Tamil 'With Heart' for National Unity | Chief Minister releases NABARD’s state focus paper 2026-27 | New initiatives to strengthen road safety in UP: Expansion of 'Sadak Suraksha Mitra' and 'Rahveer' yojana | Arunachal Police arrest 2 more from Kupwara; 5 Kashmiri men held for Pak-linked spying | From Washington to Budgam: NIA court attaches US-based separatist Fai’s property | Ahead of New Year, surveillance stepped up along Mata Vaishno Devi route | Joint security exercise held in Srinagar to counter potential threats | Health Department refers 480 Medical Officer Posts to JKPSC | Northern Railway introduces ‘scratch rake’ to curb fog delays | ‘Jan Bhagidari’ cornerstone of people-centric security: Prez Murmu | Winter vacations announced for colleges | Police seek vigilance clearance for promotion of inspectors | Kashmir parts get fresh snowfall | Fog delays over 270 flights | Back Issues  
 
news details
ULB's undue largesse towards executing agency
No penalty recovered for delay in works
2/12/2019 11:22:35 PM
Early Times Report
Jammu, Feb 12: Urban Local Bodies Department has shown undue leniency towards an executing agency which was engaged for construction of dwelling units and allied works in different parts of the State for undue delay in execution of works.
More shockingly, the department instead of taking action against the executing agency has paid excess amount to it without specific reasons, thereby causing huge financial loss to the department.
Sources told Early Times that the ULB had allotted a contract to an agency for construction of over 350 dwelling units and allied works at different locations of the state nearly seven years ago. "As per contract conditions, the work had to be done within 12 to 18 months. Due to slow pace in execution and abandonment of works half-way by the agency, all the works were retendered," they said further adding that the agency had to be imposed penalty of Rs 25 lakh as provided under the terms and conditions of the contract which was not done by the department.
They further added that against allotted cost Rs 50 lakh for construction of units, an amount of Rs 1 crore and it has been learnt that no record was kept for excess payment.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU