Breaking News :   Artificial Intelligence & Agricultural Extension Education | No Place For Terror | Cong absent as CM Omar joins campaign trail | Mining mafia: Kupwara, Samba lead in illegal mineral extraction, transportation | DGP Prabhat reviews Kashmir security | ED raids premises of ex-minister, searched | CM approves Rs 19.99 crore ‘Used Water Management Project’ for Ganderbal | Illegal immigrants grab jobs, pose security threats: Amit Shah | Poonch Police seize Rs 8.5 lakh property | Daily wagers march to CM’s residence in Jammu | Sharma, Gupta take oath as newly elected members of Rajya Sabha | PM Modi to inaugurate commemoration event today | LG Sinha pays obeisance | IFS officer Sridhar transferred to J&K | Searches underway in Kishtwar | Gold prices climb | Firecrackers banned in Poonch | Back Issues  
 
news details
ULB's undue largesse towards executing agency
No penalty recovered for delay in works
2/12/2019 11:22:35 PM
Early Times Report
Jammu, Feb 12: Urban Local Bodies Department has shown undue leniency towards an executing agency which was engaged for construction of dwelling units and allied works in different parts of the State for undue delay in execution of works.
More shockingly, the department instead of taking action against the executing agency has paid excess amount to it without specific reasons, thereby causing huge financial loss to the department.
Sources told Early Times that the ULB had allotted a contract to an agency for construction of over 350 dwelling units and allied works at different locations of the state nearly seven years ago. "As per contract conditions, the work had to be done within 12 to 18 months. Due to slow pace in execution and abandonment of works half-way by the agency, all the works were retendered," they said further adding that the agency had to be imposed penalty of Rs 25 lakh as provided under the terms and conditions of the contract which was not done by the department.
They further added that against allotted cost Rs 50 lakh for construction of units, an amount of Rs 1 crore and it has been learnt that no record was kept for excess payment.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU