Breaking News :   Justice For Terror Victim Families | Kathua Administration welcomes first Batch of Amarnath Yatris at Lakhanpur | Yatra of resilience: LG to flag off first batch today after Pahalgam carnage, Op Sindoor | LG visits Yatri Niwas at Bhagwati Nagar, reviews arrangements | LG reviews final preparations | LG chairs high-level meeting, discusses issues of terror victim families | LG flags off fleet of ambulances in Ramban, Anantnag districts | 5 real brothers from Budgam among fraudulently selected candidates | Hope beneath the surface: Govt plans underground hospital in Poonch | ACB catches DDC member red handed | Crime Branch books J&K Bank officers, others for frauds | Back Issues  
 
news details
Commissioner Secretary Kumar reviews Parnai Hydel Project, Power Scenario in Poonch
7/28/2019 11:17:57 PM
Early Times Report

POONCH, July 28: Commissioner Secretary Power Development Department (PDD), Hirdesh Kumar, today visited Poonch to review progress on Parnai Hydro Project. He also took stock of overall power scenario in the district.
In this regard, a meeting was convened in which Commissioner Secretary reviewed progress on 132KV line, installation of 50MV A transformer at Draba and works being executed under DDU, PMDP(U) and IPDS.
The meeting was attended by DDC Poonch, Rahul Yadav, Chief Engineer PDD, CPE Pernai HEP, SDMs of Mendhar and Surankote, SEs of PDD and Hydraulic, Executive Engineers and representatives of executing agencies.
During the meeting, Commissioner Secretary was apprised that payment issues of 132KV line and 50MVA transformer at Draba have been resolved. Besides, work on 132KV line is expected to be completed by the end of this year while 50MVA transformer shall be installed by the end of Aug. 2019.
Chief Engineer and representatives of executing agencies apprised Commissioner Secretary of different infrastructural interventions under PMDP(U), DDU and IPDS.
Under these schemes, 4 new substations are being created and 5 substations are being augmented in Poonch besides new DTs and HT/LT extension work is also being taken up under these schemes. It was informed that 70 per cent of these works are expected to be completed by the end of this year.
Kumar directed DDC to regularly review progress achieved on these power infrastructure augmentation works so that these are completed within the set timeframe.
Earlier, the Commissioner Secretary visited the Parnai Hydro Project, reviewed progress on different works and fixed timeline for completion of the project. He was informed about component-wise details of the project including Barrage work, HRT, Power House, Adits, Surgehufts, Penstock etc.
He exhorted Patel Engineering Limited to accelerate the construction work by deploying adequate number of machines and manpower at all sites. He was accompanied by DDC Poonch Rahul Yadav and other concerned officers during the visit.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU