x

Like our Facebook Page

   
Early Times Newspaper Jammu, Leading Newspaper Jammu
 
Breaking News :   Forces thwart Pak’s Hamas-style attack on Jammu | In Pak terrorists are given state funerals: Foreign Secretary | Terror nexus exposed: Al-Qaeda backs Pak | Jammu mosques, madrassas open for displaced border residents | Amid cross border shelling, CM Omar reviews situation in border districts | Breeding Ground for fidayeen, links to Hamas, stockpiled NATO arms | PM meets secretaries, stresses on alertness | Masood Azhar’s brother killed: BJP | LG Sinha chairs high-level meeting, reviews preparedness | Army uses Harpy drones to target enemy air defence systems | Pak attempts to attack 15 places in North, Western India foiled | 100 terrorists, aides killed in strikes: Rajnath at All-Party Meeting | SDRF conducts Mock Drill Exercise at IIT Jammu | Developed India strikes back at provocateurs by entering their hideouts: CM Yogi | Cash Row: CJI recommends impeachment of Justice Yashwant Varma, says sources | Amit terms AI as biggest disruptive tech of 21st Century in MZU National Workshop | Salman Sagar appointed as vice provincial president of JKNC | SET exam in J&K, Ladakh UTs postponed | ASCOMS & Hospital to provide free treatment to border shelling victims | Rs 300 crore BrahMos Missile Unit set to be inaugurated in Lucknow on May 11 | Any military attack on India will be met with very firm response: EAM Jaishankar | Vivek Bali Expresses Deep Grief Over Loss of Lives in Poonch Due to Pakistan Shelling | Reasi police foil illegal transportation of Khair logs in Katra area | 84 Bn CRPF Provides Relief to Flood-Affected Families | DC Jammu Reviews Zonal Master Plan for Ramnagar Eco-Sensitive Zone | Horticulture Department Kathua organises exposure visit | DC conducts on site inspection of restoration works on NH-44 | Power shut down in several areas | GMC Doda organises Blood Donation Camp | HPS participates in annual “Save Water, Save Birds” campaign | World Red Cross Day observed at Udhampur | Reasi Administration celebrates World Red Cross Day | ACR reviews implementation of E-Waste Management Action Plan | Poonch Administration steps up restoration of Essential Services, Supplies | Arushi Kotwal of Doda Honoured by Union Minister Dr Mansukh Mandaviya | Mini-Super Bazar M-PACS Maitra inaugurated in Ramban | DC Reasi felicitates JK Board Class 10th 12th Toppers | Back Issues  
 
news details
Power Department pays interest of Rs 17.49 crore, fails to produce 219.30 million units
Kalnai Hydel Electric Project suffers loss of Rs 11.20 crore
1/31/2021 12:15:24 AM
early times report
jammu, Jan 30: Thanks to the lackadaisical approach of helmsmen Power Department, 48 MW Lower Kalnai Hydel Electric project has suffered a loss of Rs 11.20 crore and control over the execution of contract for design and engineering led to an unfruitful expenditure of Rs 25.30 crore.
As per the documents in possession of the Early Times, commissioning of 48 MW Lower Kalnai Hydel Electric Project led to unfruitful expenditure of Rs 25.30 crore. The Jammu and Kashmir State Power Development Corporation Limited could not generate 219.30 Million Units of energy per annum and had to pay an interest of Rs 17.49 crore on the term loan availed for the project. The company also failed to sequence the payment of consultancy fee with the progress of the contract which led to avoidable expenditure of Rs 6.57 crore. Despite encashment of bank/ performance guarantee of Rs 79.20 crore, the Company suffered a minimum loss of Rs11.20 crore.
The erstwhile state government granted in August 2013 approval for Design, Engineering and Commissioning of 48 MW, Lower Kalnai Hydel Electric Project (LKHEP) with an estimated completion cost of Rs 576.87 crore, including escalation during construction.
The expected design energy of the project was envisaged as 219.30 Million Units (MUs), per annum. The Jammu and Kashmir State Power Development Corporation Limited awarded in September 2013 contract for Design, Engineering and Commissioning of LKHEP on EPC44 mode to a firm at a cost of Rs 396 crore for completion within 48 months from the date of award of contract i.e by September 2017. As per the stipulation of the notification of award, the contract agreement was to be signed within 30 days from the date of issue of notification of award. The Company in October 2013 also engaged another firm as Project Management Consultant (PMC) for the work, at a cost of Rs 10.39 crore. Audit scrutiny of the records of Executive Engineer, Civil Construction Division-II LKHEP, Thathri revealed that the contractor failed to furnish performance security and seven and half months were lost between issuance of notification of award and signing in 23 April 2014 of contract agreement. The work started in May/ June 2014, was executed at a very slow pace, as only 6.39 per cent progress Rs 25.30 crore was achieved in October 2017. Despite assurances, the contractor failed to finalise the design and engineering activities and accelerate execution of work. Company did not take any action against the contractor for delay.
Time extension sought (July 2017) by the contractor was not granted and the Company decided (September 2017) to terminate the contract. However, the bank/ performance guarantee of Rs 79.20 crore available with the Company was only encashed (September 2017) and the contract was not terminated. After incurring the expenditure of Rs 65.68 crore, the project work was suspended (October 2017) and could not be resumed (December 2018). Company could not generate envisaged 219.30 MUs of energy annually, valuing Rs 78.73 crore49 and had to pay an interest of Rs 17.49 crore during 2015-19, on the term loan of Rs 45 crore availed for the project.
Despite encashment of bank/ performance guarantee of Rs 79.20 crore, Jammu and Kashmir State Power Development Corporation Limited could not recover the expenditure of Rs 90.40 crore50 incurred on the project so far and suffered a minimum loss of Rs 11.20 crore.
Documents reveal that due to deficient contract management, the payment of consultancy fee to PMC was not sequenced with the progress of work of the EPC contract. Payment clause, among other things provided that the interim payments for consultancy services rendered were to be made in monthly intervals upon presentation/ compilation of the monthly invoices by the consultant. Company released 70 per cent (Rs 7.23 crore) consultancy fee, against 6.39 per cent (Rs 25.30 crore) work executed by the EPC contractor (February 2018), thereby resulting in avoidable expenditure of Rs 6.57 crore.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU