Breaking News :   ADC Rajouri flags off 40 farmers for 7-day Interstate Exposure Training to Himachal Pradesh | MVD Rajouri cracks down on violators; seizes 3 E-Autos, issues 13 challans, imposes Rs 32000 penalty | Reasi police acts swiftly against drug consumption; three cases registered under NDPS Act | DC Doda reviews District Level Telecom Committee meeting | BJP National President arrives in Lucknow for the first time, CM Yogi introduces ministers and party workers to him | One-day training programme conducted under ATMA at village Chak Drab Khan | Joint inspection of fertiliser and pesticide dealers conducted in Kathua | Shri Amarnath Yatra must become festival of economic prosperity for Jammu along with faith: Shiv Sena | Govt Polytechnic Jammu first in J&K to complete PM Vishwakarma Advanced Training | Director IIIM kick-starts the season's lavender harvest at Bonera Farm | Dimaagi Mind Care & Research Centre concludes 15-day Summer Internship in Clinical and Counselling Psychology | MY Bharat delegation calls on SMVDU Vice Chancellor to strengthen youth engagement and experiential learning collaboration | MCM strengthens employability through industry-oriented Skill Enhancement Courses | Ban controversial book, probe its approval: LoP Sunil Sharma | PM inaugurates semiconductor facility at Sanand; says youth will power AI with indigenous chips | Constructive ideas build leadership, not sloganeering or disruptions: Om Birla | RL Gupta reviews arrangements for Begum Akbar Jehan's death anniversary, Delhi protest at Jantar Mantar | Div Com chairs Airfield Environment Management Committee Meeting | Jammu police, SDRF rescue four children stranded in River Tawi | Reasi police initiates disposal of vehicles U/S 52-A of NDPS Act | ARTO Bandipora conducts Special Enforcement Drive; 37 vehicles Challaned | ADDC Kulgam reviews implementation of Mission YUVA in district | Medical Health Check-up Camp held for drivers and cleaners in Doda | UP rapidly advancing towards the digital identity of farmers | Sakeena Itoo visits Nandimarg, holds Public Darbar | Congress workers hold protest after Sunderbani meeting; former MLC & Congress | PCC condoles death of Najam-ud-Din of Ramban | General Category People's Front holds meeting | Dr Vivek Sharma announces statewide BTSM celebrations honouring His Holiness Dalai Lama's 91st birthday | Indian Army organises Gujjar-Bakarwal meet at Mori | Indian Army organises Quami Ekta meet at Dharamkot, Bhaderwah, Doda | JKTF Zone Miran Sahib bids emotional farewell to veteran Teacher Bachan Lal | President Jandiyal Biradari announces Office bearers, WC members | Met issues orange warning of heavy to very heavy rains on July 6 and 7 | Security Wing JNK Police, CCTV Unit recoveres lost bag with cash and valuables and returned to Yatri | Amit Shah to inaugurate Delhi govt's mega plantation drive on July 7: CM Rekha Gupta | Southwest monsoon to cover parts of Gujarat, Punjab, Haryana and Rajasthan in next 4 days: IMD | HC refuses to quash FIR in Sarwal police post attack case | Kishtwar police registers POCSO case, accused arrested following prompt action | No criminal case for dual MRP in 2016: HC | Indian Army peacekeepers honoured with United Nations Medals for exemplary service in Eastern DRC | LG Sinha reviews management of Amarnath Yatra 2026 | 23 more added to terrorists list, total reaches 57; HM Shah reaffirms zero-tolerance against terror | Books glorifying terrorists, separatists banned; 8 officials suspended high-level probe ordered | Coalition cracks deepen: Karra writes to CM over alleged assault on Cong MLA | DGP Prabhat reviews Amarnath Yatra security, chairs high level meet | CM Omar thanks GoI for suspending Srinagar Airport runway closure | Sex racket busted in Akhnoor, 3 arrested | Parliament session to commence from Jul 20 | Curb pirated content: Govt to Telegram | Landslide blocks Ramnagar-Udhampur road | Man killed in land dispute | Cop dies after falling unconscious | PM inaugurates SJVN’s 1000 MW Bikaner Solar Power Project | “LFO-BHF distribute 1000 sanitary napkins at Balgran | CAs key pillars of nation’s economic strength, vital partners in realizing vision of Viksit Bharat: CM | Chief Minister pays Tribute to Baba Lakhi Shah Banjara | AIKS welcomes judicial intervention in migrant ration case | Yadavindra Garden in Pinjore to be redeveloped at a cost of Rs 90 crore | PM Modi inaugurates NHPC’s 300 MW Karnisar Solar Power Plant in Rajasthan | KVK Reasi promotes solar fencing system in Monkey prone areas | 5-day peace education programme workshop concludes | NCC cadets felicitated for outstanding participation in National Camps | DIET Doda hosts Seminar on ECCE, FLN | Inner Wheel Club Jammu Tawi honours senior doctors | Water woes trigger protest: Jagti migrants gherao Relief Office | Bringing ease to citizens and businesses – The 11 year legacy of digital India | The power of positive thinking | Impact of Climate Change on Jammu and Kashmir | The Language of Oneness: When Praise Becomes Breath | Curse of ethnol blending | “Beyond Power Generation: India’s Coal Chemistry Vision” | Back Issues  
 
news details
15 yrs on, Rs 22 crore spent, ‘Check Dam’ project still incomplete
3/23/2025 10:38:52 PM
Early Times Report

Jammu, Mar 23: Fifteen years after its inception and with Rs 22 crore already spent, a ‘Check Dam’ project aimed at conserving water and supporting irrigation remains incomplete in Jammu's Kathua district.
The issue was raised by BJP’s Bharat Bhushan in the assembly through an unstarred question, seeking information about the present status of the project and the government’s response to complete the 30 percent balance work.
Responding to the query, minister in-charge Jal Shakti department Javed Ahmed Rana said the check dam at village Khokhyal was taken up in 2009 at a total cost of Rs 25.85 crore and after completion of 70 percent work of weir part of the project, the inhabitants of the area forced the department to stop work till settlement of their land compensation cases.
Various components of the project, including main check dam, left and right side guide bunds except damaged portion, diversion channel, Barmori canal RD 0-4960 metre (presently dam
BJP MP Bharat Bhushan sought information about the present status of the project.
Bhushan sought the government’s response to complete the 30 percent balance work.
The project was taken up in 2009 at a total cost of Rs 25.85 crore.
After completion of 70 percent work of weir part of the project, the inhabitants forced the department to stop work till settlement of their land compensation cases.
ged at several spots) were completed at a cumulative expenditure of Rs 22.65 crore ending March 31, 2024, he said.
The minister said the amicable solution to the land dispute took a long time due to which price escalation affected the project and the work remained incomplete and is abandoned for want of additional funds. He said a revised Detailed Project Report was submitted to the Central Water Commission (CWC) Delhi for sanction.
However, the CWC has returned the DPR with the observation that the scheme is a part of cluster of 54 Surface Minor Irrigation (SMI) schemes included under Accelerated Irrigation Benefits Programme (AIBP) during 2007-08 and central assistance has been released to the scheme under AIBP. Therefore, the project may not be revised under minor irrigation, Rana said.
In order to complete the balance work, he said a comprehensive proposal is under formulation by taking into account the changed site conditions and shall be prepared in due course of time.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU