Breaking News :   Dr Farooq urges party cadre to stand with people amid inclement weather | 18-hour mobile blackout in rural Udhampur exposes telecom failure; villagers left cut off | Govt committed to boost sports infrastructure across J&K, provide facilities in far flung areas: DyCM | Four FIRs registered for violating mandatory tenant verification orders | Gool police rescue snow trapped passengers | SSP Jammu holds security review meeting ahead of R-Day 2026 | Dialogue on sanitation conducted in various trains in Jammu division | ADG Armed reviews functioning of IRP 18th Battalion at District Police Lines: Facilities inaugurated | Labour Commissioner J&K reviews implementation of PM-SYM scheme | Police rescue 12 persons stranded due to heavy snowfall in Basantgarh area | Inter-District drug peddler arrested with heroin at Rehambal | Extension of Atal Pension Yojana reinforces Modi Government's resolve for social security: Balbir | India Ranks among Global AI Leaders; Gaurav Gupta welcomes Vaishnaw's Davos Rebuttal | Gandhi Nagar Welfare Society celebrates 2nd Anniversary of Ram Mandir Pran Pratishtha | Illegal liquor consignment seized; one booked under Excise Act | Netaji Subhas Chandra Bose continues to inspire us to stand firm against anti-national forces: Yogi Adityanath | Basant Panchmi celebrated with religious fervour at Mathwar Devsthaan | After officials, CM Omar meets stakeholders to gather inputs | J&K issues high-danger avalanche warning in 6 Districts | Northeast Frontier Railway continues construction works on Dimapur-Kohima Rail Project | Incessant Rain, Snow: 891 MW power supply restored instantly after disruption: JPDCL | Police foil bovine smuggling bid, 40 bovines rescued | Rape trial hit by forensic lapse: Court seeks CFSL pen drive, orders IO's personal appearance | DIG UR range chairs Ops-cum-Crime review meeting at DPL Udhampur | Doda admin organises live streaming of PM SVANidhi Credit Card scheme launch | Former MP Avinash Rai Khanna calls for "Screen Time to Green Time" | Simplifying policies and swift decisions have made Uttar Pradesh business-friendly under the Yogi government | ADC Ramban discusses Youth Engagement Plan, seeks suggestion from stakeholder departments | Brotherhood and Diversity: Pillars of India’s National Strength | Girl Child : Marching towards a new Horizon | New Digital Interface | True faith lives in selfless service: LG Sinha | First kill of 2026: Security forces neutralise Jaish terrorist in Kathua | Snowstorm paralyzes J&K | Mata Vaishno Devi Yatra suspended | Army pays tributes to martyred soldiers | Northern Army Commander reviews inter-agency core group security | Back Issues  
 
news details
15 yrs on, Rs 22 crore spent, ‘Check Dam’ project still incomplete
3/23/2025 10:38:52 PM
Early Times Report

Jammu, Mar 23: Fifteen years after its inception and with Rs 22 crore already spent, a ‘Check Dam’ project aimed at conserving water and supporting irrigation remains incomplete in Jammu's Kathua district.
The issue was raised by BJP’s Bharat Bhushan in the assembly through an unstarred question, seeking information about the present status of the project and the government’s response to complete the 30 percent balance work.
Responding to the query, minister in-charge Jal Shakti department Javed Ahmed Rana said the check dam at village Khokhyal was taken up in 2009 at a total cost of Rs 25.85 crore and after completion of 70 percent work of weir part of the project, the inhabitants of the area forced the department to stop work till settlement of their land compensation cases.
Various components of the project, including main check dam, left and right side guide bunds except damaged portion, diversion channel, Barmori canal RD 0-4960 metre (presently dam
BJP MP Bharat Bhushan sought information about the present status of the project.
Bhushan sought the government’s response to complete the 30 percent balance work.
The project was taken up in 2009 at a total cost of Rs 25.85 crore.
After completion of 70 percent work of weir part of the project, the inhabitants forced the department to stop work till settlement of their land compensation cases.
ged at several spots) were completed at a cumulative expenditure of Rs 22.65 crore ending March 31, 2024, he said.
The minister said the amicable solution to the land dispute took a long time due to which price escalation affected the project and the work remained incomplete and is abandoned for want of additional funds. He said a revised Detailed Project Report was submitted to the Central Water Commission (CWC) Delhi for sanction.
However, the CWC has returned the DPR with the observation that the scheme is a part of cluster of 54 Surface Minor Irrigation (SMI) schemes included under Accelerated Irrigation Benefits Programme (AIBP) during 2007-08 and central assistance has been released to the scheme under AIBP. Therefore, the project may not be revised under minor irrigation, Rana said.
In order to complete the balance work, he said a comprehensive proposal is under formulation by taking into account the changed site conditions and shall be prepared in due course of time.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU