Breaking News :   LG Sinha calls for conserving, restoring natural systems | J&K reports Rs 193.49 crore bank fraud in 2025-26 | Facebook under fire over removal of PM Modi’s video; Parliament seeks accountability | Income Tax Deptt recovers Rs 12,121 crore in crackdown on fake tax relief claims | Dream debut: Pacer Auqib Nabi gets India test call-up | CM congratulates J&K’s MMA star Owais Yaqoob on historic BRAVE CF 107 victory | 2 die in Kashmir as multiple cloudbursts, flash floods wreak havoc | In 2026, 35 cloudbursts claimed 31 lives across J&K | PM Modi hails India’s 39-medal haul at Glasgow Commonwealth Games | Amarnath Yatra crosses 4.64 lakh, fresh batch of 1,056 arrives in Kashmir | CBI Court rejects bail of postal assistant in trap case | Soldier loses life in accidental fire | Cabinet to meet today | Man held with grenade, anti-national posters | Beyond Junk Food: Building a Healthier Childhood, a Stronger India | Change the definition of Friendship on this Friendship Day | National Pride and Democratic Rights | Tricolour Flies High In Glasgow | BJP betrayed trust of Jammu people, failed to fulfil promises during "double engine" era: Sadhotra | Devyani Rana announces on spot Rs 15 lakh out of CDF for Public Projects at Nagrota Main Bazaar | Governor Kavinder Gupta calls for people's movement for environmental conservation | Military-Civil Integration Vital for Strong Defence: Rajnath Singh | Morning Walkers felicitated Er Mengi | Jammu police and BSF conduct joint anti-tunnel search operation along International Border Allah | Sakeena Itoo leads mega outreach programme of Social Welfare department at Baramulla | Rekha Mahajan calls upon women to lead social change at IWC Jammu Tawi installation ceremony | University of Jammu organizes INNOVTALKS on Vegetables for Nutritional Security Amid Climate Change | Apni Party presses for ameaning talks between centre and J&K people | 27 Trainees Successfully Complete Training on Soft Toy Making and Selling | Shri Machail Mata Yatra witnesses smooth pilgrim movement | Court rejects bail to accused linked to JeM's Nagrota strike | Power shut down | CDS addresses participants at fourth edition of Tri-services future warfare course | 171 Guns Sent on Forged Permit: Himalaya Arms Proprietor Gets One-Year Jail | Power shutdown by KPDCL | Farooq, Omar conveyed condolences | Govt approves Rs 10.95 crore for restoration, upgradation of shrines | One-Week Orientation on Contemporary IT Skills Begins for DYD Students | CM Bhagwant Singh Mann led Punjab Vidhan Sabha pays tributes to departed souls | Indian Army organised a month long plumbing skill development programme | Orientation of Masters, MBA and PhD Students at NIPER held | Back Issues  
 
news details
15 yrs on, Rs 22 crore spent, ‘Check Dam’ project still incomplete
3/23/2025 10:38:52 PM
Early Times Report

Jammu, Mar 23: Fifteen years after its inception and with Rs 22 crore already spent, a ‘Check Dam’ project aimed at conserving water and supporting irrigation remains incomplete in Jammu's Kathua district.
The issue was raised by BJP’s Bharat Bhushan in the assembly through an unstarred question, seeking information about the present status of the project and the government’s response to complete the 30 percent balance work.
Responding to the query, minister in-charge Jal Shakti department Javed Ahmed Rana said the check dam at village Khokhyal was taken up in 2009 at a total cost of Rs 25.85 crore and after completion of 70 percent work of weir part of the project, the inhabitants of the area forced the department to stop work till settlement of their land compensation cases.
Various components of the project, including main check dam, left and right side guide bunds except damaged portion, diversion channel, Barmori canal RD 0-4960 metre (presently dam
BJP MP Bharat Bhushan sought information about the present status of the project.
Bhushan sought the government’s response to complete the 30 percent balance work.
The project was taken up in 2009 at a total cost of Rs 25.85 crore.
After completion of 70 percent work of weir part of the project, the inhabitants forced the department to stop work till settlement of their land compensation cases.
ged at several spots) were completed at a cumulative expenditure of Rs 22.65 crore ending March 31, 2024, he said.
The minister said the amicable solution to the land dispute took a long time due to which price escalation affected the project and the work remained incomplete and is abandoned for want of additional funds. He said a revised Detailed Project Report was submitted to the Central Water Commission (CWC) Delhi for sanction.
However, the CWC has returned the DPR with the observation that the scheme is a part of cluster of 54 Surface Minor Irrigation (SMI) schemes included under Accelerated Irrigation Benefits Programme (AIBP) during 2007-08 and central assistance has been released to the scheme under AIBP. Therefore, the project may not be revised under minor irrigation, Rana said.
In order to complete the balance work, he said a comprehensive proposal is under formulation by taking into account the changed site conditions and shall be prepared in due course of time.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU