Breaking News :   Sikh Sangat of Jammu thanks Omar Abdullah-led Government for assurance of Punjabi language inclusion as official language in J&K | CS Dulloo reviews multi-pronged traffic management plan for Jammu, Srinagar | Devyani Rana Interacts with Progressive Farmers of Dansal at Jindrah | Dr Darakhshan reviews ongoing development works at major shrines in Jammu | Power Tariff Hike: A matter of serious concern for trade and industry in J&K | CBC Multimedia Exhibition in Katra showcases 12 years of development and public welfare | Reasi police strengthens police-public bond through Thana Diwas, focuses on grievances redressal and drug-free society | Reconstructive Eye Surgery at AIIMS Jammu: Multidisciplinary approach in syndromic child | Urges media to combat misinformation, promote social harmony and highlight public issues | Candidate in waitlist can’t jump merit queue for appointment: High Court | Shridhar story outshines at Navratra Festival-2026 in Katra | Court dismisses criminal revision against FIR registration order | Abhinav Anand meets DC Minga Sherpa IAS, extends best wishes | Drug trade thriving, organised crime growing in Punjab: Amit Shah | ITMS generates 2.8 lakh e-challans in J&K | Reasi police organises debate competition on “National integrity at Arnas | Adv Bukhari welcomes new Rajouri DC, seeks priority attention to healthcare services | Cong, allies seeking Bangladesh-like regime change: Rajnath Singh | Week-long eye care camp concludes at SDH Bhaderwah | Ladakh redraws its map: Sankoo becomes 8th district, gets its own Hill Council | Multiple search operations launched in Poonch | Govt clears Rs 1195 cr investment plans to upgrade 25 ITIs in Maha, Odisha, J&K | ACB registers FIR against officials, private persons | Missing SPO found dead | CBI arrests SMC ward officer | Govt hikes windfall tax on Petrol | The Environmental Burden of Digital Lifestyles: The Story of Invisible Pollution | Before We Graduate, Let Us Live Our Student Life | J&K’s Sporting Future Full Of Promise | J&K Prosecution's strong advocacy leads to dismissal of bail pleas in Narco-Terror, Fraud Case | Change in Train Number of Budgam - Shri Mata Vaishno Devi Katra Train | MLA Arvind Gupta inaugurates Rs 30 lakh lane and drain works in Anand Vihar | BOSE constitutes grievance- redressal cell ahead of annual exams | Jammu police foils bovine smuggling bid under PP Manwal | L-G VK Saxena announces Sankoo as Ladakh's eighth district; five new tehsils also created | SPMR College of Commerce in Men Section and GCW Gandhi Nagar in Women Section Lift | Secretary PD&MD reviews key Developmental Initiatives, Departmental Priorities | Central University of Jammu organises two-day programme | FCS&CA Anantnag observes World Food Day | Back Issues  
 
news details
15 yrs on, Rs 22 crore spent, ‘Check Dam’ project still incomplete
3/23/2025 10:38:52 PM
Early Times Report

Jammu, Mar 23: Fifteen years after its inception and with Rs 22 crore already spent, a ‘Check Dam’ project aimed at conserving water and supporting irrigation remains incomplete in Jammu's Kathua district.
The issue was raised by BJP’s Bharat Bhushan in the assembly through an unstarred question, seeking information about the present status of the project and the government’s response to complete the 30 percent balance work.
Responding to the query, minister in-charge Jal Shakti department Javed Ahmed Rana said the check dam at village Khokhyal was taken up in 2009 at a total cost of Rs 25.85 crore and after completion of 70 percent work of weir part of the project, the inhabitants of the area forced the department to stop work till settlement of their land compensation cases.
Various components of the project, including main check dam, left and right side guide bunds except damaged portion, diversion channel, Barmori canal RD 0-4960 metre (presently dam
BJP MP Bharat Bhushan sought information about the present status of the project.
Bhushan sought the government’s response to complete the 30 percent balance work.
The project was taken up in 2009 at a total cost of Rs 25.85 crore.
After completion of 70 percent work of weir part of the project, the inhabitants forced the department to stop work till settlement of their land compensation cases.
ged at several spots) were completed at a cumulative expenditure of Rs 22.65 crore ending March 31, 2024, he said.
The minister said the amicable solution to the land dispute took a long time due to which price escalation affected the project and the work remained incomplete and is abandoned for want of additional funds. He said a revised Detailed Project Report was submitted to the Central Water Commission (CWC) Delhi for sanction.
However, the CWC has returned the DPR with the observation that the scheme is a part of cluster of 54 Surface Minor Irrigation (SMI) schemes included under Accelerated Irrigation Benefits Programme (AIBP) during 2007-08 and central assistance has been released to the scheme under AIBP. Therefore, the project may not be revised under minor irrigation, Rana said.
In order to complete the balance work, he said a comprehensive proposal is under formulation by taking into account the changed site conditions and shall be prepared in due course of time.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU