Breaking News :   Longest Serving PM | Dowry system: A Social Evil Haunting Modern India | Tourism in Jammu and Kashmir | The Growing Woes of Women in the Scorching Heat | “A Gender war or A failure of law?” | From Art 370 abrogation to building Ram Temple: Amit Shah salutes PM Modi’s 12-year journey | Video becomes flashpoint at Delhi meeting as Congress high command pulls up J&K leaders | We must translate scientific knowledge into public health action: LG Sinha | 5-member high-level committee to probe Gulmarg Gondola malfunction | CM Omar meets Railway Minister Vaishnaw, seeks enhanced rail connectivity for J&K | NIA Court issues proclamation against Hizb Chief, 3 others in 1996 case | Army Chief reviews ops preparedness at Northern Command | Fire guts two dozen hutments in Kathua | Forest blaze sparks mine blasts in Rajouri | Police officer involved in narcotics case 'disengaged' from service | Panels formed to inspect hostels | Rusted mortar shell found | Jammu police and Distt Administration demolished 3 properties of drug kingpins | Union MoS Defence Sanjay Seth hails Dr Darakhshan for Hazratbal reconstruction & beautification | BIS JKBO organizes "Manak Samvaad" for newly granted licensees | Sakeena Itoo visits several areas in DH Pora, holds public outreach programme at Ahmadabad, Kulgam | Vedic wisdom emphasizes balance between material and spiritual progress: Swami Ram Swarup Ji | Youth empowerment at core of Omar Govt's vision: Javed Rana | SP City Jammu chairs Thana Diwas programme at police station bus stand | Governor Kavinder Gupta calls for making voluntary service a way of life | MLA Arvind Gupta inaugurates Rs 70 lakh lane and drain project in Hazuri Bagh | Capacity Building Programme for J&K Accounts Service Probationary Officers concludes at NZATI Jammu | DC Doda holds Block Diwas at Kari Ghuraka, directs time-bound redressal of public grievances | DC Srinagar hands over fully equipped Ambulance to BMO Hazratbal | Panun Kashmir holds preparatory meeting for international Refugee Day observance | Samba police crackdown on narcotics smuggling; 2 notorious drug peddlers arrests | Doda police traced two missing persons and reunited them with their families | DIG Udhampur-Reasi range flagged off ‘Mindal Mata Yatra’ from Udhampur | CAT cracks whip on health dept, sets 8-week deadline with Rs 1 lakh cost | Jammu police foils major bovine smuggling bid; 39 bovines rescued, 2 vehicles seized | Decision taken to add extra coaches in trains from Kanyakumari and Tirunelveli to Katra in view of additional summer rush | VC SKUAST-K holds SAC meeting of KVK Ganderbal | JKTJAC deputation meets DSEJ, raises burning issues | UP will continue to make its best contribution to nation-building under the PM's leadership: Chief Minister | Back Issues  
 
news details
15 yrs on, Rs 22 crore spent, ‘Check Dam’ project still incomplete
3/23/2025 10:38:52 PM
Early Times Report

Jammu, Mar 23: Fifteen years after its inception and with Rs 22 crore already spent, a ‘Check Dam’ project aimed at conserving water and supporting irrigation remains incomplete in Jammu's Kathua district.
The issue was raised by BJP’s Bharat Bhushan in the assembly through an unstarred question, seeking information about the present status of the project and the government’s response to complete the 30 percent balance work.
Responding to the query, minister in-charge Jal Shakti department Javed Ahmed Rana said the check dam at village Khokhyal was taken up in 2009 at a total cost of Rs 25.85 crore and after completion of 70 percent work of weir part of the project, the inhabitants of the area forced the department to stop work till settlement of their land compensation cases.
Various components of the project, including main check dam, left and right side guide bunds except damaged portion, diversion channel, Barmori canal RD 0-4960 metre (presently dam
BJP MP Bharat Bhushan sought information about the present status of the project.
Bhushan sought the government’s response to complete the 30 percent balance work.
The project was taken up in 2009 at a total cost of Rs 25.85 crore.
After completion of 70 percent work of weir part of the project, the inhabitants forced the department to stop work till settlement of their land compensation cases.
ged at several spots) were completed at a cumulative expenditure of Rs 22.65 crore ending March 31, 2024, he said.
The minister said the amicable solution to the land dispute took a long time due to which price escalation affected the project and the work remained incomplete and is abandoned for want of additional funds. He said a revised Detailed Project Report was submitted to the Central Water Commission (CWC) Delhi for sanction.
However, the CWC has returned the DPR with the observation that the scheme is a part of cluster of 54 Surface Minor Irrigation (SMI) schemes included under Accelerated Irrigation Benefits Programme (AIBP) during 2007-08 and central assistance has been released to the scheme under AIBP. Therefore, the project may not be revised under minor irrigation, Rana said.
In order to complete the balance work, he said a comprehensive proposal is under formulation by taking into account the changed site conditions and shall be prepared in due course of time.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU