Breaking News :   Justice For Terror Victim Families | Kathua Administration welcomes first Batch of Amarnath Yatris at Lakhanpur | Yatra of resilience: LG to flag off first batch today after Pahalgam carnage, Op Sindoor | LG visits Yatri Niwas at Bhagwati Nagar, reviews arrangements | LG reviews final preparations | LG chairs high-level meeting, discusses issues of terror victim families | LG flags off fleet of ambulances in Ramban, Anantnag districts | 5 real brothers from Budgam among fraudulently selected candidates | Hope beneath the surface: Govt plans underground hospital in Poonch | ACB catches DDC member red handed | Crime Branch books J&K Bank officers, others for frauds | Back Issues  
 
news details
AIIMS Jammu getting only 7 vehicles of gravel daily despite need of 50
Shortage of minor mineral hampering mega projects
3/3/2021 11:14:20 PM
Early Times Report
JAMMU, Mar 3: The ban on minor minerals in Jammu region is hampering many mega projects. For any construction work whether government or private one needs gravel, sand and other allied products for carrying out construction which is not presently available.
Presently, Jammu and other adjoining districts are dependent on Kathua from where the material is being supplied. The construction material being supplied from Kathua is not sufficient to meet the present market need and in such circumstances the work on the building of All India Institute of Medical Sciences, Vijaypur is badly hampering.
According to reports, the construction work is badly hampering due to the non-availability of minor mineral as the site has a requirement of around fifty vehicles a day but is getting only seven vehicles.
AIIMS is a dream project for the people of Jammu region but if the work will go on like at snail's pace it is not going to be completed in stipulated time period. The delay in the completion of the project will further burden the government's kitty following escalation in prices of many products.
The people of Jammu region were very happy after the work on AIIMS was started but it seems that they still have to rush to Delhi or other States for speacialized treatment following delay in construction of AIIMS Vijaypur. Sources said that the construction work was in full swing but following shortage of material is now standstill from almost last one and half month.
According to DMO Kathua, Devinder, tendering process of River Ravi is over but majority of stone crushers in the area are sealed and district has very limited resources which cannot fulfill the demand of entire Jammu region.
Vijay Kumar, a local shopkeeper from Vijaypur, said that the people were very excited to have AIIMS in their area and the work earlier was also in full swing and double shift but now it is going on snail's pace which may take more years in completion than deadline.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU