Breaking News :   Initial probe reveals involvement of some ponywallas, street vendors | Don’t give sermons: India sends strong message to West | Fear-stricken Pak seeks Iran's help to de-escalate tensions with India | ‘India cuts water flow through Baglihar dam’ | Irregularities surface in APD transfer order, multiple officers posted on single posts | Amid India-Pak tensions, IAF Chief calls on PM Modi | SC reconstitutes 3-Judge bench to hear pleas against upholding ED powers | Monitor top advance tax payers: CBDT to IT Deptt | IGP Kashmir chairs joint security review meet | 3 soldiers die in Ramban accident | Army receives new supplies of Russian missiles | Pak troops violate ceasefire for 10th day | Portals of Badrinath open | 4 arrested for taking money from NEET aspirants | Strong Message | Ajaz Jan urges India, Pakistan Nuclear Nations to prioritize civilian safety, avoid escalation | SSP Doda conducts extensive tour of far off areas, held PCPG meetings, reviewed VDGs | Doors of Badrinath shrine open on Sunday amidst Vedic chants | CRPF Constable sacked for "Concealing" marriage to Pak woman claims he informed higher-ups | BSF to get 16 new battalions, 2 field HQs for Pak, Bangla borders | New Election Commission platform to subsume 40 mobile, web Apps | NEET-UG held at over 5,400 centres under strict security, no reports of untoward incidents | Unite against divisive forces, uphold idea of inclusive India: Sadhotra tells youth | Ashok Koul, Arvind hold key meeting with Ward 41 delegations, Kashmiri Samaj members | SSP Jammu chairs crime and security review meeting at DPL Jammu | Silent crisis growing burden of heart disease in rural India: Dr Sushil | Punjab: Two held in Amritsar on charge of spying | India looking for partners, not preachers: Jaishankar's message to Europe | I Wasn't There During Many Congress' Mistakes, But Happy To Take Responsibility: Rahul | Sadguru Madhuparamhans Ji reveals secrets of eternal realm in Akhnoor | Absconder arrested by Jammu police in Pallanwala area | Natrang stages Hilarious Hindi Play 'Aag Ka Tamasha' in Sunday Theatre Series | Kavinder inaugurates blood donation camp | Two nabbed with heroin-like substance by Samba police | Suresh Sharma inaugurates 63 KVA transformer and passenger shed in Devnagar village | Six gamblers caught red-handed by Samba police | Truck seized for illegal timber smuggling in Jammu's Gharota area | Amity meeting organised by Indian Army with Civil Society | Indian Army conducts medical patrol for locals | Shantmanu, ACS Higher Education launches Newsletter | Netball Association of J&K opens player registrations for 2025-26 championships | Kuldeep can be extremely valuable in English conditions: Experts | Delhi Capitals take on Sunrisers Hyderabad hoping to break two-match losing streak | Lahiri finishes 45th as DeChambeau registers first win of the season | Aditi Ashok shoots 66 and rises to tied-20th at Black Desert | Kedarling Uchaganve leads Army 1-2 in men's air pistol at KSSM | Bhullar falters in final round, drops to 54th in Korea | Back Issues  
 
news details
Sordid saga of Jehangir Chowk-Rambagh flyover
Minister sets deadlines, forgets them later
3/16/2018 11:28:20 PM
Early Times Report

Jammu, Mar 16: The dilatory mode of functioning in the state government could be gauged by the fact that with just two weeks away from the set deadline, the completion of much hyped Jehangir Chowk-Rambagh is far from completion.
As per the insiders, it was impossible that the project would get completed in mere 14 days as the deadline was set by the government as March 31, 2018. "It remains to be seen what would be the new deadline for the completion of the project as merely 60 percent of the work is finished with rest going on at a snail's pace. The government itself seems be clueless as the delay is taking heavy toll on vehicular movement in the summer capital," said an official privy to the development.
Last year in November, labourers and technicians had gone on strike at the site for their pending wages. Due to such a development, the project missed the deadline of its first phase which was earlier set as December 31, this year. The project, on which work began in 2013, is funded by Asian Development Bank (ADB) and executed by Economic and Reconstruction Agency (ERA). The 2.4-km flyover missed many deadlines due to dispute with shopkeepers, floods in 2014 and 2016 uprising. Its completion is expected to reduce the travelling time from Jehangir Chowk to Hyderpora and will ease traffic jams in the city.
Meanwhile, appending wide scale backlash over snail's pace work, the government has tasked the Divisional Commissioner Kashmir to personally monitor the work over the fly over.
Reports inform that the R&B is being slammed by one and all in Valley over the way it is monitoring the work of the flyover- the construction of which has led to total chaos in the summer capital- resulting in traffic mess and prolonged snarls.
Interestingly, the incumbent R&B minister while setting one more deadline had stated that the first link of the flyover connecting Amar Singh College with Barzulla will be operational by the end of August 2017. However, the Div Com in November stated that the first link will get operational by the end of 2017.
Recently, a high level meeting was held in Srinagar that was chaired by the Div Com Kashmir. It was informed in the meeting that the total cost of the Jehangir Chowk-Rambagh flyover project was Rs 262 crore and the first phase of the project from Rambagh-Amar Singh College would be completed by ending December 2017.
Taking the control now in his own hands, the Div Com directed contractors to enhance the scale of labour at the site so that the project is completed in a fixed timeline.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU