Breaking News :   Doctors - The Unsung Heroes of Healthcare | WHEN RS 10 FEELS EXPENSIVE ON A CART, BUT NOT IN A CAFE | Urdu For Naib Tehsildar Recruitment Test | Yatri Niwas in Srinagar | LG Sinha inaugurates SASB Yatri Niwas at Pantha Chowk | LG launches campaign for zero-waste pilgrimage | 'Amarnath Yatra arrangements upgraded' | Heroin worth Rs. 420 crore seized in Rajasthan; Pak-based smuggler, Canada handler named | Within minutes after formation of PAC, NC mocks Sajad Lone’s new political front as ‘BJP’s B-Team’ | CM Omar calls for revival of buyer-creator relationship at SKICC Meet | Salal Dam gates opened amid rising Chenab Water levels | DGP chairs joint security review meeting in Anantnag, visits key areas | Major reshuffle in ACB J&K | From warzone to homeland: Kashmiri students hail India’s rescue mission with tricolour cheers | Security Forces bolster security with hi-tech gadgets | Token distribution for registration begins | Security Forces conduct joint mock drill | India woman footballer Soumya undergoes surgery after nasal bone fracture | Lack of variety in India's bowling attack is concerning: Chappell | National-level minor boxer alleges sexual harassment by woman coach | | MCM launches workshop on Skill Development, Entrepreneurship | GDC Kathua honours NCC Cadet Mohit Kanathia with grand welcome ceremony | Missing person traced from Pallanwala within 2 days | JKHCBAJ unveiles Portrait of Maharaja Hari Singh ji, inaugurated | Four JKAS Officers transferred In Transport Dept Reshuffle | J&K police arrest 87 in drug crackdown, seize narcotics worth Rs 2.42 Cr | Gross GST collections double in 5 years to record Rs 22.08 trillion in FY25 | Srinagar police attaches residential property worth Rs 50 lakh | SKUAST-K holds workshop in Gurez to promote revival of heritage crops | Reasi police solves two theft cases in Katra, accused arrested, stolen property | Union Minister Piyush Goyal to lead transformative FTII Traders conclave | Congress holds impressive Jai Hind Yatra in Poonch City, salutes armed forces, martyrs | Warm, affectionate farewell accorded to retirees of Agriculture Department Jammu | DC Shopian inspects work of rural development projects at Keller | Former JKNPP leaders, senior workers join Apni Party | Committee on Petitions holds meeting in Srinagar | 6000 students participate in NMMSS examination | Ladakh PM Vishwakarma artisans participate in MSME Day celebration | Vi Business’s ready for next - India’s largest digital advisory celebrates growth on MSME day | Indian Army pays tribute to Ex-Serviceman | Civil Defence, Jammu started 5 days CD training programme | Warm send off accorded to Sardar Dharminder Singh Bhargav Head Pharmacist from DHS-J | JKEDI concludes second batch of MDPs in 10 districts | Handicrafts, Handloom Deptt condoles demise of father of Mussrat Islam | IGNOU launches certificate programme for Nurse Managers to Strengthen Managerial Competencies in Nursing Services | Back Issues  
 
news details
Rs 1.50 cr spent, but truck terminal at Doda still incomplete
11/21/2018 11:26:57 PM
Early Times Report
Jammu, Nov 21: The faulty Detailed Project Report (DPR) prepared by Urban Local Bodies for the construction of truck terminal building at Doda has badly affected the project even after Rs 1.50 crore has been spent on it so far.
Sources told Early Times that the commencement of work without proper site survey at time of preparation of DPR and before commencement of work for construction of the truck terminal resulted in delay in completion of work despite expenditure of Rs 1.50 crore and doubling of its cost to Rs 3.20 crore.
"A project for construction of truck terminal building at Doda was sanctioned in 2011-12 for providing separate parking space for trucks and tippers and loading/ unloading of goods. The ULB Division-II Jammu got prepared the DPR for geo-technical and architectural design, for an estimated cost of Rs 1.60 crore which was accorded administrative approval.
Sources said the amount of Rs 1.60 crore was released during 2012 to 2016 by the ULB Jammu for construction to the executing agency with completion period of nine months. During execution, the site of the building was shifted to lower contours due to which quantities of various items of work like earthwork, concrete and back filling of earth got increased and work up to only roof level could be completed after spending Rs 1.50 crore.
Sources further informed that the division submitted revised DPR at the cost of Rs 3.20 crore which had not been approved and the work stands held up resulting in non-completion of building despite incurring expenditure of Rs 1.50 crore.
It was observed that the detailed structural drawings was not prepared before preparation of the DPR and the existing road width was assumed as 10 metres instead of 3.50 metres which resulted in shifting of main building by 8.900 metres towards lower contour level, resulting in increase in the quantities of various items of work.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU