Breaking News :   J&K Fire Services Recruitment Scam: 103 appointees terminated after ACB probe | Vijay Saraf scripts history, polls 2006 votes in Amar Singh Club elections | CM Omar draws line, says INDIA bloc not part of Congress’s ‘Vote Chori’ campaign | NIA files chargesheet; names accused, Court fixes Jan 5 as next hearing date | HM Shah recalls Sardar Patel’s unparalleled contribution | Police arrest 2 main accused within hours | J&K Sports Minister assures fair probe into team selection for Santosh Trophy | Court extends NIA custody of Soyab, Naseer Bilal by 4 more days | 60 flights cancelled at Delhi Airport | Raj Kumar Goyal sworn in as CIC | 60 flights cancelled at Delhi Airport | Night temperature improves in Kashmir | Rupee to close at all-time low against US Dollar | FAQ on VB- G RAM G Act 2025 | Childhood: Then and Now - A Shifting Landscape | Human Judgment Must Prevail | CS releases publications on climate change and floriculture in J&K | DG BSF visits Jammu International Border | MLA Ch Vikram Randhawa launches pipeline work to end water scarcity in Channi Himmat | Criminals involved in attempt to murder case arrested within 24 hours by police | People of Katra be made stakeholders in all development initiatives; not pushed off path to survival: Rattan Lal Gupta | ‘Vote Chori is Congress' Political DNA: Gaurav | SSP Felicitates Officers/ Officials of PCR Jammu for Outstanding Performance in Inter-Zone Police Sports Meet 2025 | CS calls for mission-mode implementation of DPIIT set district business reforms | AIIMS Jammu launches advanced Interventional Cath Lab Services | DB upholds 1979 police batch's seniority; quashes adverse orders | Debt-ridden Latur resident murders drunk man to fake his own death for Rs 1 cr insurance; arrested | Nitin Nabin takes charge as BJP national working president; Nadda, Shah facilitate | Govt to bring bill replacing MGNREGA with new law guaranteeing 125 days of wage employment | Bill to create single higher education regulator introduced in LS | Prime Minister congratulates Indian Squash Team on World Cup Victory | Udhampur police attaches drug peddler's immovable property worth Rs 35 Lakhs | Advisory for pilgrims regarding booking through HGOs/PTOs for Haj 2026-regarding | DBU Chancellor Dr Zora Singh honoured by Punjab Governor at All India Media Meet | Div Com Kashmir Reviews Progress of Operationlisation of 60 MLD STP for Srinagar city | DC Kupwara reviews various land issues pertaining to defense | Anantnag police organizes drug awareness programme | KVK Bandipora organises Technology Demonstration on Aquatic Crop Cultivation | MCM faculty visit Anandpur Sahib | BCCI not recognised as NSF: Sports Minister Mandaviya in Lok Sabha | Jammu outplays Srinagar to clinch U-19 Boys UT Softball Title at Katra | GGM Science College Red Ribbon Club organises walkathon to Mark World AIDS Day 2025 | GDC Ramnagar organises Awareness Lecture on “Campus to Community: Drug Free India” | St Mary’s Infant Convent School unveils “Wings of Wonder” at 11th Annual Day | Back Issues  
 
news details
Rs 1.50 cr spent, but truck terminal at Doda still incomplete
11/21/2018 11:26:57 PM
Early Times Report
Jammu, Nov 21: The faulty Detailed Project Report (DPR) prepared by Urban Local Bodies for the construction of truck terminal building at Doda has badly affected the project even after Rs 1.50 crore has been spent on it so far.
Sources told Early Times that the commencement of work without proper site survey at time of preparation of DPR and before commencement of work for construction of the truck terminal resulted in delay in completion of work despite expenditure of Rs 1.50 crore and doubling of its cost to Rs 3.20 crore.
"A project for construction of truck terminal building at Doda was sanctioned in 2011-12 for providing separate parking space for trucks and tippers and loading/ unloading of goods. The ULB Division-II Jammu got prepared the DPR for geo-technical and architectural design, for an estimated cost of Rs 1.60 crore which was accorded administrative approval.
Sources said the amount of Rs 1.60 crore was released during 2012 to 2016 by the ULB Jammu for construction to the executing agency with completion period of nine months. During execution, the site of the building was shifted to lower contours due to which quantities of various items of work like earthwork, concrete and back filling of earth got increased and work up to only roof level could be completed after spending Rs 1.50 crore.
Sources further informed that the division submitted revised DPR at the cost of Rs 3.20 crore which had not been approved and the work stands held up resulting in non-completion of building despite incurring expenditure of Rs 1.50 crore.
It was observed that the detailed structural drawings was not prepared before preparation of the DPR and the existing road width was assumed as 10 metres instead of 3.50 metres which resulted in shifting of main building by 8.900 metres towards lower contour level, resulting in increase in the quantities of various items of work.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU