JAMMU, July 18 : In order to carry out the work of erection, testing and commissioning of 132 KV Isolator in 132 KV bay at 50 MVA, 132/33 KV Grid Station Mahanpur, the shutdown of 1 x 50MVA, 132/33 KV Grid Station Mahanpur on 19-07-2014 from 7 a.m. to 2 p.m. is allowed. As intimated by Chief Engineer, S&O Wing Jammu, during the shut down period, no power supply shall be affected. Only one circuit of Sewa-Mahanpur 132 KV D/C Transmission Line will remain off during the above period and Grid Station Mahanpur will be charged on Kathua-Mahanpur 132 KV transmission line through back feed. Meanwhile, in order to carry out shifting of load from 33 KV BB-II to 33 KV New Kartholi line, the power supply to the Industrial area Bari-Brahmana, EPIP Kartholi and adjoining areas fed from 33 KV BB-II and 33 KV New Kartholi line shall remain affected on 20th of July 2014 (Sunday) from 9 a.m. to 1 p.m. In order to carry out branch cutting of trees under 33 KV GG-2 & GG-3 lines feeding R/stn Gangyal, Seora and Babliana, the power supply to the Trikuta Nagar, part of Industrial area Gangyal, Seora, Babliana and its adjoining areas fed from 33/11 KV R/Stn. Gangyal, Seora and Bablina, shall remain affected on 20th of July 2014 (Sunday) from 6 a.m. to 9 a.m. |