Breaking News :   Heartbreaking scenes as symbolic funerals held for 3 missing members of Digiana family | Vaishno Devi Yatra may resume on first Navratra | AAP’s political play: Turning Mehraj’s PSA case into expansion drive in J&K | Life returning to normal in Doda | PM Modi to visit Bihar today | 'Cong backing Pak-groomed terrorists' | CB books directors of pvt company, scammers, Govt employee among 8 for big frauds | 3 terror sympathisers arrested in Poonch | ‘Develop legal, tech solutions to act against elements behind AI-based fake news’ | Respect all Indian languages: Amit Shah’s appeal on Hindi Diwas | Man shoots himself dead | Cross-border drug smuggling attempt foiled | From decay to dynamism: How Modi is rebuilding Urban India | Remembering Pt.Tilka Lal Taploo& Other Martyrs | Linguistic Harmony | FICCI FLO JKL distributes flood relief material under in Jammu | Rise in dengue cases matter of concern: Balbir | TWS, Public Works Department collaborate to bring relief to flood affected communities | LG Kavinder pays obeisance at Siddhivinayak Temple | Drug peddler arrested with Heroin in Rehambal | DFC will unlock trade potential for Uttar Pradesh | Dr Manohar demands immediate relief to flood-affected victims | Viksit UP @2047: AI, biotech, green energy, and agritech to shape global identity | NHPC conferred with Rajbhahsha Kirti Puraskar | IIM Jammu conducts cleanliness drive as part of Swachhata Pakhwada | Restoration of critical connectivity on Mahanpur-Theyn Axis completed by BRO | Captain Tushar Mahajan Memorial Trust awards eminent educationist & meritorious students | "Hindi Hai Hind Ki Dhadkan" vibrant celebration of Hindi Diwas held at Pallanwala | 13th Triennial General Council of SBI Officers' Association, held at Panchkula | Indian Army conducts medical patrol in remote village of Rajouri | DD@66 - Doordarshan Foundation Day 2025: Shabdanjali | Liberty introduces two new technologies for Nation | Microplastics, Nanoplastics - Hidden Threats to Cardiovascular Health: Dr Sushil | Restore promised statehood to J&K to rebuild trust in democracy: Rattan Lal Gupta | SSP Udhampur chairs Ops-cum-Crime review meeting at DPL Udhampur | Textiles & Handicrafts Store at Srinagar Railway Station allotted through e-auction | Two Thieves Arrested, Stolen Motorcycle, Mobile Phones & Cash Recovered by Police | Interaction With ESM, Veer Naris & Widows at Jamola Rajouri | Crackdown on illegal mining by Samba police, seizes 14 vehicles including 6 dumpers | 9 vehicles including in illegal mining seized by Police | Public meeting of YRS held regarding upcoming celebration of Maharaja Hari Singh Ji Birth Anniversary | KPBB brings hope to flood-hit Jammu with discipline, compassion | IIM Jammu inaugurates second batch of Management Development Program | PM Modi writing golden chapter of J&K history: Rohiin Chandan | Centre for Molecular Biology, CUJ hosts Induction cum Orientation program | Dr. Sanjay Mohan delivers expert talk on Innovation, Startup Ecosystem Enablers | NMC urges PM to release pending instalments of DA | Spellbound performance on Bollywood Singer‘s Dogri Songs | Natrang Sunday theatre play “Shrimaan X” | BSF organises Medical Camps in Flood-Affected Areas in Jammu region | Department of Environmental Sciences organized Aurora 2025 - Orientation Programme | Back Issues  
 
news details
Who will fix responsibility for irregular execution of works in PWD?
Receipt of funds incorrectly projected, authorities in a fix
1/11/2022 11:28:13 PM
Early Times Report

Jammu, Jan 11: Reports pertaining to the receipt of funds incorrectly projected as having been executed are coming to the fore in the R&B department with details emerging about payment of Rs 2.23 crore was made for 61 works.
Documents reveal that the Chief Engineer, PW (R&B) Department, Jammu forwarded in April 2016 to the Commissioner Secretary, PW(R&B) Department, a statement of work done claims amounting to Rs 155.47 crore in respect of 276 roads for sanctioning of funds under the project. The statement included work done claims of Rs 4.57 crore in respect of eight works pertaining to four Divisions. The works are (1) Main Road Trikuta Nagar including allied links (2) Road from Macca Masjid and Main Road Gulmarg Colony including allied links (3) (i) Satwari to Technical Gate (Double Lane : 400 Mtrs) (ii) Technical Gate to MH Gate (Double Lane: 600 Mtrs), (iii) Satwari Chowk to Manik Shah Chowk (Three Lane: 650 Mtrs) (iv) Manik Shah Chowk to Technical Gate (Three Lane: 550 Mtrs) (4) Kullian Laswara road including link road to Draptha Village (50 mm thick BM +25 mm thick SDBC) (5) City Road in Jammu West Constituency (a) Rehari Chungi to Patoli via Sarwal (b) Rehari Chungi to Patoli via Subash Nagar and Toph Chowk (c) Subash Nagar to Shiv Nagar (d) Rehari colony to Shakti Nagar via Rajpura (e) Patoli Chowk to Paloura Chowk (f) Main Bakshi Nagar Road (g) Rehari Colony to Maheshpura Chowk via Baby Caterers (h) Canal head to Toph Bridge via A.G. Office including road Toph Chowk via Best price (6) Kamini mohalla Nagrota (7) Ghagwal Town road, Ghagwal Rajpura Road (3.00 km Double lane and 4.50 km Single lane) and Ghagwal - Raghu Chak Malani road and (8) Dayalachak-Hiranagar-Jandi road (single lane) in the divisions namely Construction Division (CD I), Jammu (4), CD II, Jammu (2), Kathua (1) and Samba (1)
However, these eight works in actuality were awarded for execution between May 2016 and March 2017 after furnishing of statement of work done claims to higher authorities in April 2016. The Chief Engineer, PW (R&B) Department, Jammu has submitted to the government that a work-wise action plan of macadamization-to paves by laying and compacting successive layers of broken stone, with water, asphalt, or hot tar- of roads for Rs 200 crore was submitted in February 2016 for approval and accordingly, the Administrative Department released work-wise funds.
However, as per the documents, an amount of Rs 11.26 crore was sanctioned in August 2016 and March 2017 to I&FC Division, Poonch for 159 works executed after the floods of September 2014 to clear the outstanding liabilities. Of this, payment of Rs 2.23 crore was made for 61 works which were, however, executed between August 2016 and March 2018 after the receipt of funds incorrectly projected as having been executed.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU