jammu, Aug 30: In order to carry out relay testing through primary and secondary injection of 132 KV and 33 KV side and preventive maintenance of various equipment at 132/33 KV Grid Station Sidhra, the shut down of 2x 20 MVA, 132/33 KV Grid Station Sidhra on August 31, 2015 from 6.30 a.m. to 10 a.m. is allowed. As intimated by Chief Engineer, S&O Wing Jammu, during the shutdown period the power supply to Janipur, Jhajjar Kotli, Bahufort, Sidhra, ASCOMS, Malori Jagir, Bajalta and Toota-de-Khoi as both circuits of 132 KV Gladni-Sidhra and Sidhra-Janipur Transmission line shall be affected. |