Breaking News :   Jammu symbol of India’s national unity: LG Sinha | LG unveils J&K Bank 2026 calendar | Biggest development leap of 2025: 30-year wait ends as trains finally reach Kashmir | Recruitment fraud case: EOW Kashmir chargesheets TDPI Director | NIA Court issues proclamation notice against ex-KCCI Prez Mubeen Shah, 2 others in 2020 UAPA Case | Indian Oil completes highest-ever winter stocking in Ladakh | Amid ongoing anti-terror ops, Army trains VDGs in Doda | Searches underway in Kishtwar, Poonch | PM Modi calls for mission-mode reforms to sustain growth | Unclaimed bag sparks bomb scare | MeT forecasts rain, snow in Kashmir | Traffic resumes on Mughal Road | Wildlife Conservation | 2025 - The Year of Reforms | 2025 – A Decisive Year for Naxal Mukt Bharat | HC refuses to quash ACB FIR against ARTO, clears way for chargesheet in DA case | AIIMS-Jammu proposes Traumatology Institute, Centre for AI in healthcare | DC Ramban reviews drug control measures | Ladakh Admin facilitates safe evacuation of stranded passengers | Amit moderates 2nd UTLCCC meeting chaired by CS Ladakh | MLA Haveli Ajaz Jan graces concluding ceremony of Zia-Ul-Uloom's 'PlayFest' in Poonch | Public meeting held by SSP traffic rural Jammu | CS launches online NDC service, releases annual calendar and administrative reforms handbook of ARI & Trainings Deptt | Full Court reference held to bid farewell to Justice Vinod Chatterji Koul | Education empowers growth, ensures a life of dignity: Balbir | NHM concludes ToT under School Health, Wellness Programme & NTCP in Jammu division | Doda police arrest another drug peddler with charas-like substance; FIR registered under NDPS Act | Haryana emerges as national leader in criminal justice reforms, tripling convictions and pioneering forensic excellence: Dr Sumita Misra | NFR achieves major ROB-RUB infrastructure milestones in 2025 | Under leadership of CM Bhagwant Singh Mann, Punjab Vidhan Sabha pays homage to unparalleled shaheedi of four Sahibzadas | Punjab Vidhan Sabha pays tributes to departed souls | DC Kathua reviews progress of PWD sector schemes | FM Harpal Singh Cheema declares ‘Viksit Bharat - Gram G’ as attack on poor, federalism | CM Nayab Singh Saini announces multiple development projects for Gurugram ahead of New Year | GMC launches initiative to provide nutritional support to over 100 TB patients | Free medical outreach camp held | CITCO Hotels Ring in New Year 2026 with celebrations at Mountview and Shivalikview | SWD provides pension benefits to transgender beneficiary | Tiger Division conducted 1212-km cycling expedition commemorating diamond jubilee of 1965 Indo-Pak war | DC Bandipora attends Career Counselling Session at Kaloosa | Mega women entrepreneurship mela held at Kishtwar | Scientists reach from 'Lab' to 'Land' for the first time | Ayodhya's transformation: Where faith fuels development and the future takes shape | 3% discount scheme on booking unreserved tickets through “Rail One” App to benefit passengers | BJP District Jammu South observes Atal Samriti Sammelan in Bahu Constituency | Natrang creates history in 2025, breaks 15-year record by staging 152 shows | CUJ organise open selection trials for Women Cricket Team | Back Issues  
 
news details
After spending Rs 1.5 lakh, SKUAST-K master plan remains incomplete
7/16/2018 12:07:09 AM
Early Times Report

Jammu, July 15: Despite spendind 1.5 lakh, SKUAST-K master plan remains incomplete.
Moreover the monitoring aspect of various undergoing projects was overlooked widely by the University authority which has adversely affected their completion due to disinterest shown by the Planning Committee.
Sources told Early Times that the main objective of the preparation of Master Plan was to ensure the best use of the land of University for infrastructure development and the decision in this regard was taken in 2011 by the authority concern. Subsequently the contract for preparation of Master plan was allotted to a firm at a cost of Rs 7 lakh. "The firm had prepared only an interim report along with set of maps indicating the existing site plan and the site analysis and Rs 1.5 lakh was paid to the firm for the job.
Adopting laxity, the University neither issued notices to the firm for completion of the job nor was the task entrusted to any other firm," they said further adding that not only this even the non-monitoring of projects which was entrusted to Planning Committee not done sincerely.
As per sources, the Planning Committee of the University was to monitor major projects including the University projects as a whole and had to issue guidelines on their observations and for this the Planning Committee was required to meet four times in a year. Against 20 mandatory meetings required to be held during 2011-16, only one meeting had been held during the period of five years. "Thus, monitoring of projects being implemented in the University had not been ensured and guidelines for planning of programmes for proper implementation had not been evolved," they informed.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU