4 sewerage projects in Jammu expected to be completed by March 2017: Govt
5/31/2016 11:28:03 PM
Ishtiyaq Ahmad

Early Times Report

Srinagar, May 31: The Jammu and Kashmir government Tuesday informed that four sewerage Projects in Jammu city are under implementation and are expected to be completed by March 2017.
In a written reply to legislative Assembly, the Deputy Chief Minister who is also the Housing and Urban Development Minister of the state has said that four sewerage projects in Jammu city are under implementation namely 'Comprehensive Sewerage scheme phase Ist Greater Jammu, Sewerage Treatment Works for left out areas Phase II division A of Greater Jammu, Procurement of Sewerage Plant (STP) of 30 MLD Capacity at Bhagwati Nagar, Jammu and Sewerage Project Phase II ( Left out poration of Talab Tilloo.
The Deputy Minister has mentioned in the reply that the project Comprehensive Sewerage scheme Phase Ist Greater Jammu has been sanctioned by GOI under JnNURM during 2008.09 at a cost of Rs. 129.23 Crore and is executed by NBCC. An amount of Rs. 64.74 crore has been incurred up to March, 2016.
He has said that project sewerage network for left out areas phase II division A of Greater Jammu was also approved by GOI under JnNURM during 2011, 2012 at a cost of 20.32 crore and against which an amount of rupees 3.08 crore were utilized up to March 2016.
Nirmal Singh has informed that as both these projects were sanctioned under JnNURM for which the GOI has stopped release of funds.
However he has claimed that request has been made to GOI for providing the balance funds for the incomplete projects of JnNURM under newly launched AMRUT mission. Singh has informed that the procurement of sewerage plant (STP) of 30 MLD capacity at Bhagwati Nagar, Jammu is executed by ERA and is funded under ADB at a cost of rupees 156. 56 crore against which an amount of 104.62 Crore has been utilized up to March, 2016. The expected date of completion for the project is on March, 2017. He has said that sewerage Project phase II (left out portion of Tallab Tillo) is funded under state plane at a cost of rupees 14.39 crore against which an amount of rupees 9.07 crore has been utilized up to March 2016.The expected date of completion is March 2017 subject to availability of funds.
The total expenditure incurred on these comprehensive sewerage schemes from 2009 to 2016 is 181. 4 crore.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
top stories of the day
Ministers', babus' kin adjusted in Govt Press
BJP MLA who draws no salary has many schemes to make 'illegal money'
Mehbooba decries NC for doing politics over her ‘pigeons among cats’ remark
Govt's 'dual' approach
PDP's 'Tridev' faces party whip
Malik's arrest unnerves Geelani, Mirwaiz
Cong digging its own grave in Jammu
Principal MHAC Nagbani was harassing teacher since 2014: Police
Social welfare department turns haven for blue eyed
DSP suspended over family feud
BJP's henchmen drain exchequer by taming PWD engineers
'Crime against women on rise in J&K: Khour rape victim faces threat'
Allegations of mass copying at IGNOU center Chatroo
Revenue minister assures probe into encroachment of District Hospital, Sports Stadium Doda
Ex-minister's directives ignored
Backdoor appointments in RDD rock LC
Who created Salahuddin? Legislators trade blame
Land acquisition in Budgam: SIC directs Tehsildar to reveal info
Govt Allocates Rs 2 Cr for Construction of Toilets in Police Stations
Rashid, Akbar Lone's open spat in LA
Mendhar under acute 'water strife'
Pungent Dal weeds test tourists' patience
Poppy cultivation continues as drug addiction increases in Valley
It's official: Mehbooba to contest by-polls from Anantnag
Jammu Chamber threatens shutdown
LC members take strong exception to Rashid's statement, walk-out from House
Govt asks DCs to fix monthly targets for removal of encroachments
Will House set up committee to probe 295 kanal Humhama scam?
4 sewerage projects in Jammu expected to be completed by March 2017: Govt
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU