early times report JAMMU, JANUARY 03-In order to carry out erection of 220 KV SF-6 Circuit Breaker at Grid Station Hiranagar, the shutdown of 200 MVA bank at 320 MVA, 220/132/66 KV Grid Station Hirangar, the power supply to Kathua, Hiranagar, Samba, Billawar and Bari-Brahmana shall remain affected on January 05, 2014 from 10 a m to 1 p m. Similarly in order to maintain the proper ground clearance at Ravi River crossing span of D/C Sarna and Pathankot feeders, the power supply to Lakhanpur, Basantpur, CTM-I, CTM-II, Kathua-III feeder and its adjoining areas including RTIC installation shall remain affected onJanuary 04 and 05, 2014 from 9 a m to 6 p m. The shutdown shall be subject to fair weather condition
|