8 out of 12 tourism projects funded by Union Govt still incomplete
2/17/2014 10:58:03 PM
Bijay Charak

Jammu, Feb 17: The Union Government for promotion of tourism in J&K had sanctioned 12 projects in 2005-06. Funds for the projects were also released but astonishingly eight projects are still incomplete.
Documents in the possession of Early Times reveal that in fiscal year 2005-2006, six projects which were sanctioned under product infrastructure development for destination and circuits, out of which four projects were incomplete.
"The total cost of six projects is Rs.941.13 Lakhs and the amount released Rs. 782.9 Lakhs. The projects which are incomplete include Development of Integrated circuit Bhaderwah-Sinthan-Srinagar, their cost is Rs. 691.13 Lakhs and the amount released Rs. 552.9 Lakhs, another project Development of Jheri, with sanction cost of Rs. 50 Lakhs and same was released and the project status is going on", the documents read, adding that the project for Development of Gagangir, Sonamarg village their cost was Rs.50 Lakhs and Rs. 40 Lakhs has been released, another project for Development of Surinsar village of Rs.50 lakhs and Rs. 40 Lakhs for said project has also released, but projects were still laying incomplete.
It further reads that in the year 2006-2007 another project was sanction under the product infrastructure development for destination and circuits, Development of Rural Tourism in village Vasaknag Kund valley was started with an estimated cost of Rs 48.53 Lakhs. "The amount was released on same year, but the status of the project is still incomplete", the documents read.
Union Ministry of Tourism, in year 2006-07 approved a software work plan with an estimated cost of Rs. 52.26 Lakhs under the scheme of Capacity Building for Service Providers (CBSP), for the various villages include (Akingaam, Anantnag), Surinsar and Jhiri, out of which Rs 44.66 Lakhs was released but the status of work is still incomplete.
"The project cost of (Akingaam and Anantnag) software work plan was Rs. 14.26 Lakhs and same was released but the project still incomplete, similarly the other two projects software work plan for the site of village Jhiri and Surinsar were still incomplete", the data reveals.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
top stories of the day
Red-tapism in Health Deptt helps officers to fleece Contractual employees
150 employees suspended for absenteeism in Kishtwar
`Condom kay bena hasina, Kitna risk hai?
CB, SVO seek permission to prosecute 152 Govt officials in 107 cases of corruption in 3 years
SFC castigates discrimination against qualifications acquired through distance learning
Ministers come to rescue of tainted Principal Government Dental College, Srinagar
Saroori refuses Omar's offer of Cabinet berth
Administrative anomalies galore in Agriculture department
Subscribers frustrated by Reliance services, Customer Care
SIC lambasts DySP (Hqs) Jammu for withholding information
NC unlikely to mitigate hardships of refugees
Vested interests in Assembly oppose critics of Article 370
NC, Congress may loose one seat each in Kashmir and Jammu
Pandemonium in LA, opposition stages walkout over ration scarcity
Police, army launch manhunt for `dreaded' militants
Court extends judicial remand of 2 traders
Protest demonstrations at encounter sites posing challenges to security establishments
8 out of 12 tourism projects funded by Union Govt still incomplete
Taj assures 50% concession for BPL category masses
Agriculture on decline in JK as 40% farmers give up farming
Petitioner Rana likely to be dropped from committee, NC reduced to minority
Promotion, adjustment of ineligible officials continues unabated in Technical Education department
NC workers, Revenue officials involved
Opposition take Govt to task on use of pellet guns, stage walkout
Omar questions Constitution but finds faults with Kejriwal
Temple Bill Row: Select Committee to hold 'final' meeting today
JK at bottom with lowest CDR of 30.58 %, State potentially energy deficient
Members cut across lines to protest `discrimination'
Reliance promises skies, delivers zero
Congress's Kashmir policy to harm it in elections
Baigh pooh-poohs Rather's budget speech
Opposition in Kashmir to new administrative units in Jammu flawed
Only 27% representations for areas under backward classes disposed off
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU